Correct Power Off and Power On Sequence for Distribution Rooms and Step-by-Step Energizing Procedure

Echo
Field: Transformer Analysis
China

Power Off and Power On Sequence in the Distribution Room

Power-off sequence:
When de-energizing, first disconnect the low-voltage (LV) side, then the high-voltage (HV) side.

  • When de-energizing the LV side:
    First open all LV branch circuit breakers, then open the LV main breaker. Additionally, disconnect the control circuits before de-energizing the main power circuits.

  • When de-energizing the HV side:
    First open the circuit breaker, then open the isolating switch (disconnector).
    If the HV incoming line has two isolating switches, first open the load-side isolating switch, then the source-side isolating switch.

Power-on sequence: Reverse the above order.

Never operate an isolating switch under load.

Power-On Operation Procedure for the Distribution Room

The power-on procedure is as follows:

  • Confirm that no personnel are working on any electrical equipment in the entire distribution room. Remove temporary grounding wires and warning signs. When removing grounding wires, disconnect the line end first, then the grounding end.

  • Verify that the incoming line switches for both circuits WL1 and WL2 are in the open position. Then close the bus-tie isolating switch between the two HV busbars WB1 and WB2 to allow them to operate in parallel.

  • Sequentially close all isolating switches on WL1, then close the incoming circuit breaker. If the closing is successful, it indicates that WB1 and WB2 are in good condition.

  • Close the isolating switches for the voltage transformer (VT) circuits connected to WB1 and WB2, and verify that the supply voltage is normal.

  • Close all HV outgoing isolating switches, then close all HV outgoing circuit breakers to energize the main transformers of the distribution room.

  • Close the LV-side knife switch of the main transformer in Distribution Room No. 2, followed by the LV circuit breaker. Successful closing indicates that the LV busbar is intact.

  • Use voltmeters connected to both LV busbar sections to verify normal LV voltage.

  • Close all LV outgoing knife switches in Distribution Room No. 2, then close the LV circuit breakers (or close LV fuse-switch disconnectors) to energize all LV outgoing circuits. At this point, the entire HV distribution substation and its associated workshop substations are fully operational.

Restoring Power After Fault Clearance:

If power is being restored after a fault-related outage, the procedure depends on the type of switching device installed at the incoming line:

  • If the incoming line uses a high-voltage circuit breaker:
    In the event of a short-circuit fault on the HV busbar, the circuit breaker will trip automatically. After the fault is cleared, power can be restored simply by reclosing the circuit breaker.

  • If the incoming line uses a high-voltage load-break switch:
    After fault clearance, first replace the fuse cartridge, then close the load-break switch to restore power.

  • If the incoming line uses a high-voltage isolating switch with fuses (fuse-disconnector combination):
    After fault clearance, first replace the fuse tube, then open all outgoing circuit breakers. Only then may the isolating switch be closed, followed by reclosing all outgoing breakers to restore power.

  • If the incoming line uses a drop-out fuse (expulsion fuse):
    The same procedure applies—replace the fuse tube, ensure all outgoing switches are open, close the fuse, then re-energize the outgoing circuits.

Give a tip and encourage the author!

Recommended

Faults and Handling of Single-phase Grounding in 10kV Distribution Lines
Characteristics and Detection Devices for Single-Phase Ground Faults1. Characteristics of Single-Phase Ground FaultsCentral Alarm Signals:The warning bell rings, and the indicator lamp labeled “Ground Fault on [X] kV Bus Section [Y]” illuminates. In systems with a Petersen coil (arc suppression coil) grounding the neutral point, the “Petersen Coil Operated” indicator also lights up.Insulation Monitoring Voltmeter Indications:The voltage of the faulted phase decreases (in
01/30/2026
Neutral point grounding operation mode for 110kV~220kV power grid transformers
The arrangement of neutral point grounding operation modes for 110kV~220kV power grid transformers shall meet the insulation withstand requirements of transformer neutral points, and shall also strive to keep the zero-sequence impedance of substations basically unchanged, while ensuring that the zero-sequence comprehensive impedance at any short-circuit point in the system does not exceed three times the positive-sequence comprehensive impedance.For 220kV and 110kV transformers in new constructi
01/29/2026
Why Do Substations Use Stones, Gravel, Pebbles, and Crushed Rock?
Why Do Substations Use Stones, Gravel, Pebbles, and Crushed Rock?In substations, equipment such as power and distribution transformers, transmission lines, voltage transformers, current transformers, and disconnect switches all require grounding. Beyond grounding, we will now explore in depth why gravel and crushed stone are commonly used in substations. Though they appear ordinary, these stones play a critical safety and functional role.In substation grounding design—especially when multiple gr
01/29/2026
Why Must a Transformer Core Be Grounded at Only One Point? Isn't Multi-Point Grounding More Reliable?
Why Does the Transformer Core Need to Be Grounded?During operation, the transformer core, along with the metal structures, parts, and components that fix the core and windings, are all situated in a strong electric field. Under the influence of this electric field, they acquire a relatively high potential with respect to ground. If the core is not grounded, a potential difference will exist between the core and the grounded clamping structures and tank, which may lead to intermittent discharge.I
01/29/2026
Related Products
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.