Quality Control for Installation and Construction of Electrical Riser Lines and Distribution Boxes in Building Electrical Systems

James
Field: Electrical Operations
China

2.jpg

1. Introduction

Building electrical engineering is an indispensable component of modern construction projects. The installation of electrical riser lines and distribution boxes is of paramount importance to the integrity and functionality of the entire electrical system. The quality of riser line installation directly impacts the usability, safety, and operational efficiency of the entire building. Therefore, rigorous quality control measures for the construction of electrical riser lines and distribution boxes are essential to prevent economic losses and ensure occupant safety.

In public buildings, electrical risers primarily serve as the main power supply conduits for lighting, power loads, and other equipment on each floor. Any quality issues within the riser can have a direct and cascading impact on the entire building's electrical infrastructure. Thus, strict control over construction quality is critical to guarantee the overall quality of the building's electrical engineering. This ensures that all parameters comply with national construction safety standards and safeguard the normal daily lives of occupants.

2. Overview of Building Electrical Riser Engineering

The standard power supply voltage for building electrical systems is 380/220V, utilizing flame-retardant power cables. High and low voltage distribution rooms are typically located on the first basement level, with power distributed to each floor via electrical risers. The lightning protection level is classified as Grade 1, and the grounding protection system employs the TN-S configuration.

The installation of riser lines significantly influences the functionality of the entire building. Consequently, any hidden defects or improper installations within the electrical riser can pose serious safety threats to the entire construction project, potentially leading to fire hazards, electrical failures, or compromised structural integrity.

3. Preparation Work for Installing Building Electrical Riser Lines

3.1 Pre-embedding of Openings in Electrical Risers

Electrical riser rooms generally require the installation of basic auxiliary facilities such as cable trays, distribution boxes, cable bridges, and associated cabling. Prior to pre-embedding, the positions of all electrical equipment and conduits within the riser must be accurately laid out according to the design drawings. If discrepancies are found between the marked dimensions on the drawings and the actual site conditions, timely adjustments must be made to ensure the correct installation of electrical conduits and equipment at a later stage, preventing costly rework.

3.2 Precautions During the Pre-embedding of Electrical Conduits

The pre-embedding of conduits must be meticulously planned based on the height, dimensions, and specific locations of the electrical distribution boxes. This ensures that conduits are neatly aligned and unobstructed, guaranteeing the correct routing and connection of cables. The proper and correct installation of distribution boxes significantly enhances the accuracy, reliability, and aesthetic quality of the riser line connections. Therefore, the overall installation should aim to create an electrical riser that optimally combines economy, aesthetics, and reliability.

4. Quality Control for the Installation of Electrical Riser Lines and Distribution Boxes

4.1 Quality Control for Busway Installation

  • Busway Assembly and Fixing: The busway within the electrical riser must be assembled in the correct position and securely fixed. Units should be installed with uniform spacing and neat alignment to facilitate future maintenance and inspection.

  • Joint Positioning and Protection: Connection joints for the busway should not be located at floor slabs. The distance from the joint to the building floor should be a minimum of 650mm. To protect the busway during installation, its outer shell should be wrapped with plastic film to prevent physical damage or water ingress, thereby ensuring installation quality.

  • Insulation Testing: Before installation, the insulation resistance of the busway must be measured using a megohmmeter. Installation can only proceed if the resistance exceeds 20MΩ. For enclosed busways, a 2500V megohmmeter is required to measure the insulation resistance of each functional unit, which must also exceed 20MΩ. This test is critical and must be performed before and during installation.

  • Alignment and Stress Prevention: Ensure that the busbar and its outer shell are concentric, with a maximum allowable error of 5mm. This precision ensures proper alignment between busbar segments and prevents the busbar and its shell from being subjected to mechanical stress after connection.

  • Component Verification: Technicians must verify the specifications and models of all busway components against the system diagram to prevent blind installation, which can lead to rework, unnecessary losses, and compromised construction quality.

  • Plug-in Box Installation:  Insert the plug-in box into the designated opening on the busway and secure it with bolts. Connect the power from the plug-in box to the distribution box using flexible metal conduits.

  • Floor Penetration Support: When the busway passes through a building floor slab, use 1–3 bolts (matching the busway size) to fix springs and specialized support attachments. Securely connect the support to the floor slab using nuts, flat washers, bolts, and spring washers to properly support the busway column. (Refer to Fig. 1: 1 - Channel steel, 2 - Bolt, 3 - Spring support, 4 - Specialized attachment).

4.2 Quality Control for the Installation of Cable Trays and Raceways

The technical parameters for cable trays and raceways must strictly adhere to the design drawings, with a reasonable allowance reserved to ensure the correct installation of cables at a later stage. The installation must ensure the rationality of the cable tray routing and the convenience of raceway installation. On-site construction personnel must thoroughly analyze the construction drawings, understand the specified installation methods, and be prepared to make adjustments based on actual site conditions to ensure a correct and compliant installation.

4.3 Laying of Power Cables

The cable installation method must be determined by combining the electrical construction drawings with the on-site conditions, ensuring the process is effective, rational, scientific, and convenient. The two primary cable installation methods are:

  • Laying within cable trays.

  • Direct laying along brackets mounted on building walls.

Rigid protective sleeves are typically installed at points where cables are susceptible to damage (e.g., where they pass through walls or floors) to protect power cables from abrasion or impact.

5. Quality Control for the Installation of Building Electrical Distribution Boxes

  • Selection and Cost Estimation: Before      installation, the quality of the distribution boxes must be carefully      selected. While ensuring quality, costs should be minimized. The estimation formula for distribution boxes can be used: A = ∑BK + C +  D, where:

    • ∑B: Total price of all switching devices inside the distribution box.

    • K: Comprehensive coefficient (generally 1.40 according to national standards).

    • C: Price of the distribution box enclosure.

    • D: Cost of accessory materials.

    • A: Estimated total price of the distribution box.

5.1 Installation of Building Electrical Distribution Boxes

  • Positioning and Integrity: The installation position of electrical distribution boxes must be accurate,  with all components complete and undamaged.

  • Conduit Entry: Openings in the box must match the conduit diameter. Conduits should be secured using lock nuts. The conduit entry into the box should typically be 3–5mm.

  • Secure Fixing: When fixing the distribution box to the building structure, the connections must be robust and secure.

  • Installation Methods: Common methods include laying along raceways or using exposed conduits.Regardless of the method, specialized cutting tools must be used to maintain the overall aesthetics of the installation.

  • Hole Drilling: If standard knockouts do not meet requirements, new holes must be re-drilled using a sheet metal drill; punching or burning holes is prohibited.

  • Labeling and Wiring: Inside      the distribution box, all circuits and important information must be clearly and permanently labeled. Avoid drilling holes on the sides of the box to prevent incoming/outgoing wires from contacting grounding or neutral wires, which poses a significant safety hazard.

  • Accessibility: For wall-mounted distribution boxes, ensure the door can open to at least 180°  for full access to internal components.

  • Internal Wiring: Keep internal wiring neat and orderly, without any twisting or crossing . When connecting wires with pressure plates, ensure they are tightened securely to prevent loosening.

5.2 Installation of Floor-Mounted Cabinets

  • Base Support: Use channel steel as a base support for floor-mounted electrical cabinets, strictly following the dimensions and positions indicated in the drawings.

  • Conduit Entry: Conduit openings entering the cabinet should extend 50–80mm above the base of the cabinet.

  • Secure Connection: Connect the cabinet to the base channel steel using galvanized bolts and lock washers  to ensure a secure, corrosion-resistant, and vibration-resistant connection.

  • Base Height: The top of the      base channel steel should be 10mm above the finished floor level to  prevent water ingress and allow for leveling.

6. Waterproof and Fireproof Sealing of Openings in Risers

According to relevant fire protection standards, improperly sealed openings in risers can create a "chimney effect" during a fire, allowing flames and smoke to spread rapidly between floors. Therefore, all penetrations through floor slabs within the riser must be properly sealed, and this critical task requires meticulous attention from technical personnel.

  • Sealing Procedure: The      standard method involves using expansion bolts to fix a fireproof barrier (such as a fire-rated board or a 2mm thick steel plate) to the underside of the floor slab. The opening is then sealed, and the space is filled  with approved fireproof sealing material (e.g., firestop mortar, putty, or mineral wool). (Refer to Fig. 2).

  • Waterproofing: A 30–50mm high waterproof barrier (or "drip ring") should be constructed around  he top of the sealed opening to prevent water from entering the fireproof material, which could compromise its fire-resistance rating.

  • Importance: Strengthening the waterproof and fireproof sealing of riser openings is essential for  ensuring the overall construction quality and safety of the building. This task is of the utmost importance; if neglected, it could lead to catastrophic losses, affect the entire project, and pose severe threats to human life and property.




Give a tip and encourage the author!

Recommended

Faults and Handling of Single-phase Grounding in 10kV Distribution Lines
Characteristics and Detection Devices for Single-Phase Ground Faults1. Characteristics of Single-Phase Ground FaultsCentral Alarm Signals:The warning bell rings, and the indicator lamp labeled “Ground Fault on [X] kV Bus Section [Y]” illuminates. In systems with a Petersen coil (arc suppression coil) grounding the neutral point, the “Petersen Coil Operated” indicator also lights up.Insulation Monitoring Voltmeter Indications:The voltage of the faulted phase decreases (in
01/30/2026
Neutral point grounding operation mode for 110kV~220kV power grid transformers
The arrangement of neutral point grounding operation modes for 110kV~220kV power grid transformers shall meet the insulation withstand requirements of transformer neutral points, and shall also strive to keep the zero-sequence impedance of substations basically unchanged, while ensuring that the zero-sequence comprehensive impedance at any short-circuit point in the system does not exceed three times the positive-sequence comprehensive impedance.For 220kV and 110kV transformers in new constructi
01/29/2026
Why Do Substations Use Stones, Gravel, Pebbles, and Crushed Rock?
Why Do Substations Use Stones, Gravel, Pebbles, and Crushed Rock?In substations, equipment such as power and distribution transformers, transmission lines, voltage transformers, current transformers, and disconnect switches all require grounding. Beyond grounding, we will now explore in depth why gravel and crushed stone are commonly used in substations. Though they appear ordinary, these stones play a critical safety and functional role.In substation grounding design—especially when multiple gr
01/29/2026
Why Must a Transformer Core Be Grounded at Only One Point? Isn't Multi-Point Grounding More Reliable?
Why Does the Transformer Core Need to Be Grounded?During operation, the transformer core, along with the metal structures, parts, and components that fix the core and windings, are all situated in a strong electric field. Under the influence of this electric field, they acquire a relatively high potential with respect to ground. If the core is not grounded, a potential difference will exist between the core and the grounded clamping structures and tank, which may lead to intermittent discharge.I
01/29/2026
Related Products
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.