In power systems, voltage transformers in GIS (Gas Insulated Switchgear) play a crucial role in voltage measurement and relay protection. Selecting the right model and installing it correctly is vital for the stable operation of the equipment. The following points should be noted regarding selection and installation.
I. Key Points for Selection
(1) Matching Rated Parameters
  • Voltage Level: It must be consistent with the voltage level of the GIS system. For example, 110kV and 220kV GIS systems require voltage transformers of corresponding levels to ensure accurate voltage measurement and long-term stable operation of the equipment.
  • Rated Capacity: Select based on the power requirements of devices connected to the secondary circuit (such as measuring instruments and protection devices). If there are many connected devices with high power, a transformer with a larger capacity should be chosen to avoid affecting measurement accuracy or damaging equipment due to insufficient capacity.
  • Accuracy Class: Determine according to the purpose. For metering, higher accuracy classes are required, usually 0.2 or 0.5; for relay protection, 3P or 6P is sufficient.

(2) Paying Attention to Insulation Performance

  • Insulation Type: Voltage transformers in GIS commonly use SF₆ gas insulation or epoxy resin casting insulation. SF₆ gas insulation has good insulation and arc-extinguishing effects, while epoxy resin casting insulation has a compact structure and high reliability. The choice can be made according to the actual operating environment and needs.
  • Insulation Level: It must withstand the maximum operating voltage, lightning overvoltage, and operating overvoltage of the system. The higher the voltage level, the stricter the requirements for insulation level, which is directly related to the safe operation of the equipment.
(3) Emphasizing Anti-Resonance Capability
Ferromagnetic resonance may occur during system operation, which is likely to damage voltage transformers. Therefore, try to select those with good anti-resonance performance, such as those with harmonic elimination devices, to reduce the occurrence of resonance and its hazards.
(4) Ensuring Mechanical Strength
During transportation, installation, and operation, the equipment may be subject to vibration, impact, or electric power during short circuits. The structural design of the voltage transformer should be reasonable, with sufficient mechanical strength to withstand these external forces and avoid deformation or damage.
II. Key Points for Installation
(1) Checking the Installation Environment
  • Cleanliness: The interior of the GIS must be clean, without dust, metal debris, or other impurities, which may affect the insulation performance of the voltage transformer and even cause discharge faults. Before installation, the GIS air chamber should be thoroughly cleaned and inspected.
  • Sealing: The sealing of the GIS air chamber is important to prevent SF₆ gas leakage. SF₆ is the key medium for insulation and arc extinguishing in GIS equipment, and leakage will reduce insulation performance and affect the operation of the voltage transformer.
  • Temperature and Humidity: The temperature and humidity of the installation environment should meet product requirements, generally in a dry and moderately temperatured place. Excessive humidity may cause insulation to get damp and affect equipment performance.

(2) Standardizing the Installation Process

  • Hoisting and Handling: When handling and hoisting the voltage transformer, use appropriate lifting tools and operate according to the designated lifting points of the product to prevent collision, tilting, or excessive vibration, which may damage the internal structure.
  • Electrical Connection: The wiring of the secondary circuit should be correct and firm, and the connecting wires should have sufficient cross-section and insulation performance to prevent poor contact and short circuits. For the primary side connection, ensure tight connection, good conductivity, and meet current-carrying requirements.
  • Grounding Requirements: The secondary windings and shell of the voltage transformer should be reliably grounded to ensure the safety of equipment and personnel. The grounding resistance should meet relevant standards, generally not exceeding 4 ohms.

(3) Conducting Post-Installation Debugging

  • Insulation Testing: After installation, conduct insulation resistance testing and withstand voltage testing on the voltage transformer to check whether its insulation performance meets the requirements.
  • Transformation Ratio and Polarity Check: Test whether the transformation ratio meets the design value to ensure measurement accuracy; check whether the polarity is correct to avoid incorrect instrument indication or misoperation of protection devices.
  • Gas Detection (for SF₆ Insulation Type): For those using SF₆ insulation, detect the gas pressure and micro-water content in the air chamber to ensure they are within the normal range.
In conclusion, considering parameter matching and reliable performance during selection, and paying attention to the environment, process, and debugging during installation, can ensure the safe and stable operation of GIS voltage transformers and guarantee the reliable power supply of the power system.
James

Professionalism builds strength. As an expert in the installation and operation of electrical equipment, I am proficient in the installation process and strictly adhere to standards. I skillfully master the operation essentials and can swiftly eliminate faults. With a heart that constantly explores new knowledge, I illuminate the path to the efficient operation of electrical equipment.

Selection and Application of Small Reactors at the Neutral Point of 500kV Substations
Selection and Application of Small Reactors at the Neutral Point of 500kV Substations
1 Relevant Theories of Small Neutral Point Reactors in 500kV Substations1.1 Definitions and RolesA reactor is a key power system component that controls the phase relationship between AC current and voltage, divided into inductive and capacitive types. Inductive reactors limit short-circuit currents and improve stability; capacitive ones enhance transmission efficiency and voltage quality. A small neutral point reactor is a specialized type connected between a three-phase system's neutral point
Echo
07/25/2025
What are the comprehensive considerations for product selection and installation?
What are the comprehensive considerations for product selection and installation?
In real-world engineering projects, selecting and installing 35kV combined instrument transformers isn't just a matter of "buying and installing" — it requires a comprehensive evaluation of many factors, such as environmental conditions, equipment performance, and maintenance convenience. Only by taking all these aspects into account can we ensure that the equipment runs safely and stably for a long time under specific conditions.1. Oil-Immersed vs. Dry-Type Transformers — Which One
James
07/22/2025
What aspects should be considered when selecting and installing 35kV combined transformers?
What aspects should be considered when selecting and installing 35kV combined transformers?
The installation quality of combined instrument transformers directly affects whether they can operate safely and stably. Therefore, during the installation process, several key aspects must not be overlooked — such as foundation construction, grounding, sealing checks, testing and commissioning, as well as secondary wiring. Below, I’ll explain these points in a more conversational way.1. Foundation Construction Must Be Solid, Especially in Plateau AreasAlthough a combined instrument
James
07/22/2025
A Quick Verification Method for Low-Voltage Current Transformers
A Quick Verification Method for Low-Voltage Current Transformers
1. Selection of Low - Voltage Current Transformer ConfigurationThere are many factors leading to wrong selection of low - voltage current transformers in civil construction projects. For example, common factors include design problems: the calculated coefficient designed for the load of electrical equipment is relatively large, or the transformation ratio of the current transformer is selected incorrectly. Such a series of reasons will affect the use of electrical equipment. Therefore, in the co
James
07/16/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!