• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Technical Analysis of 220 kV High-Voltage Cable Construction in Winter

James
Field: Electrical Operations
China

1.Work Environment Requirements and Safeguard Measures

Based on technical requirements for cable equipment storage, laying, transportation, laying, transposition, testing, and cable terminations, the project owner and construction units have conducted extensive trials and implemented protective measures regarding ambient temperature, humidity, bending radius, traction control, and route optimization. These measures ensure high-voltage cable quality and on-site safety under harsh winter conditions.

2.1 Ambient Temperature Requirements and Safeguard Measures

The working environment humidity for cable laying must be maintained at 70% or below, with temperatures at or above 5°C. When laying cables in trenches, the temperature should not fall below 0°C, and a dust-free environment is preferred. To ensure compliance with cable laying temperature requirements, the construction unit has implemented the following measures, as shown in Figures 1, 2, and 3.

First, to ensure the safe and reliable installation of Ningxia's first 220 kV high-voltage cable, technical personnel from the cable manufacturer are required to provide full-process guidance and supervision of cable conditions. This ensures that critical stages—including storage, handling, laying, shelving, termination fabrication, and cable testing—meet relevant environmental and technical requirements.

Second, to ensure effective thermal insulation at cable storage locations, insulation sheds are erected according to plan and wrapped externally with cotton material. The outer cotton fabric is buried 10–20 cm underground. Inside the shed, electric heaters and hot air blowers provide continuous heating to maintain the outdoor cable storage temperature above the required minimum.

Third, cables are preheated for 24 hours prior to laying. After transferring cables from storage to the terminal pole, a 6m × 6m insulation shed is immediately erected. Electric heaters and hot blowers are used inside the shed for continuous heating. After 24 hours of preheating, manufacturer technicians assess whether the temperature meets the required conditions for cable laying.

Fourth, continuous thermal insulation and dust protection are maintained throughout the laying process. Plastic tarpaulins are laid along the entire cable route. The area around direct-buried cable channels is regularly sprayed with water to maintain a dust-free environment. Exposed cables are wrapped with insulating cotton cloth, quilts, and tarpaulins, while electric heaters are used inside trenches. Openings at manholes and trench ends are sealed to ensure the cable laying temperature remains within required specifications.

high-voltage cables.jpg

high-voltage cables.jpg

high-voltage cables.jpg

2.2 Cable Laying Requirements and Safeguard Measures

After the ambient temperature for cable laying meets the relevant technical requirements, the cable bending radius should be at least 120°, and the cable must not be damaged during the laying process. When mechanically pulling the cable, the maximum traction strength should preferably comply with specified values.

According to cable laying technical requirements, first ensure reliable communication. Dedicated personnel shall be assigned to supervise key locations, including inside and outside the station, each manhole entrance, and corners within trenches, under the unified command of the site supervisor to ensure safe and reliable cable installation. Second, in cable tunnels and maintenance passageways, pull ropes are deployed manually. A steel mesh sleeve is installed to replace the pulling head, and an anti-twist device is added between the cable pulling end and the traction rope. The maximum allowable traction strength during mechanical cable laying should preferably conform to the values specified in the table below.

image.png

To ensure the maximum cable traction force complies with the above requirements, four conveyors and two capstans are deployed along the cable route. The conveyors are positioned 70 m, 140 m, 210 m, and 280 m from the terminal tower, respectively, while the capstans are located 240 m and 362 m from the terminal tower, as shown in Figures 4, 5, and 6.

Finally, hoisting pulleys are suspended at the entry and exit points of the pull rope to prevent damage to the cable and rope when entering or exiting the cable tunnel. Along the straight sections of the tunnel, one straight-line ground pulley is placed every 2–2.5 meters, and one corner ground pulley is installed at each turning point. If excessive force is encountered at a corner, a hoisting pulley may be used instead to facilitate turning. Pulley placement may be adjusted appropriately along the route based on actual field conditions.

high-voltage cables.jpg

high-voltage cables.jpg

high-voltage cables.jpg

2.3 Cable Testing Requirements and Safeguard Measures

Testing must be stopped if the environmental humidity exceeds 80%. When wind speed at the test site reaches Force 4 (8 m/s), aerial test wiring work must be halted immediately.

According to relevant technical requirements for cable testing, weather conditions must first be monitored in a timely manner, with on-site wind speed measured using an anemometer. Secondly, prior to conducting cable tests, the entire reel of cable must be dried or wiped to ensure the test site meets all required technical conditions. Figure 7 shows personnel performing external insulation testing on the cable.

high-voltage cables.jpg

Give a tip and encourage the author!
Recommended
Mismatched AC Contactor Sizing? These 4 Typical Issues You Must Not Ignore – Click to View Solutions
AC contactors (with the electrical schematic code KM) are core electrical devices used to control the connection/disconnection between power supplies and loads in circuits, and they are also common equipment that electricians need to work with regularly. In practice, it is not uncommon to find that some peers make mistakes in selecting AC contactors, leading to improper sizing and subsequent persistent issues. Here, four of the most typical common mistakes are highlighted for reference.I. Over-R
James
09/11/2025
Proper Installation of AC Contactors | A Practical Guide to Avoid Burning and Misoperation, Master It in One Article
AC contactors are widely used for switching and controlling power circuits. They use main contacts to open and close circuits, and auxiliary contacts to execute control commands. Main contacts typically only have normally open contacts, while auxiliary contacts often have two pairs of contacts with normally open and normally closed functions. Small-sized contactors are also frequently used as intermediate relays to work with main circuits, thereby achieving the function of remote control or cont
James
09/11/2025
Constant testing of high-voltage cable lines
1. Definition of High-Voltage Cable Line Constant TestingHigh-voltage cable line constant testing refers to the systematic measurement, using specialized instruments, of electrical parameters such as resistance, inductance, capacitance, and conductance before a cable line is commissioned or after major maintenance. The aim is to obtain fundamental data characterizing the electromagnetic properties of the cable, serving as a critical testing phase that provides accurate parameter support for powe
Oliver Watts
09/03/2025
Withstand voltage test of high-voltage cables
Withstand voltage test is an insulation test, but it is a destructive test that can reveal insulation defects difficult to detect in non-destructive testing.The test cycle for high-voltage cables is three years, and it must be conducted after non-destructive tests. In other words, the withstand voltage test is performed only after all non-destructive tests have been passed.Most high-voltage cables used today are cross-linked polyethylene (XLPE) cables, which can have large cross-sections and cov
Oliver Watts
09/03/2025
Seed Inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.