• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Commissioning Test Procedures for Oil-Immersed Power Transformers

Oliver Watts
Field: Inspection and testing
China

Transformer Commissioning Tests Procedures

1. Non-Porcelain Bushing Tests

1.1 Insulation Resistance

Suspend the bushing vertically using a crane or support frame. Measure the insulation resistance between the terminal and the tap/flange using a 2500V insulation resistance meter. The measured values should not deviate significantly from factory values under similar environmental conditions. For capacitor-type bushings rated 66kV and above with voltage sampling small bushings, measure the insulation resistance between the small bushing and the flange using a 2500V insulation resistance meter; the value should not be less than 1000MΩ.

1.2 Dissipation Factor Measurement

Measure the dissipation factor (tanδ) and capacitance of the main insulation to the tap using the positive wiring method. Follow the instrument's specified wiring configuration and select a test voltage of 10kV.

The high-voltage test leads for dissipation factor testing must be properly suspended with insulating tape, kept away from other equipment and the ground. Implement appropriate safety measures to prevent unauthorized access to the high-voltage test area. The measured dissipation factor and capacitance values should not significantly differ from factory values and must comply with handover standards.

2. On-Load Tap Changer Inspection and Testing

Check the complete action sequence of the on-load tap changer contacts. Measure the transition resistance value and switching time. The measured transition resistance values, three-phase synchronization deviation, switching time values, and forward-reverse switching time deviation must comply with the manufacturer's technical requirements.

Oil-Immersed Power Transformer.jpg

3. DC Resistance Measurement of Windings with Bushings

Measure the DC resistance of the high-voltage winding at each tap position and the low-voltage side. For transformers with neutral points, measure single-phase DC resistance where appropriate. Record the ambient temperature during measurement to facilitate comparison with factory values after temperature conversion. The deviation between line-to-line or phase-to-phase values must comply with handover standards.

4. Voltage Ratio Check for All Tap Positions

Connect the turns ratio tester leads to the high and low voltage sides of the three-phase transformer. Check the voltage ratio for all tap positions. Compared to the manufacturer's nameplate data, there should be no significant difference, and the ratios should follow expected patterns. At the rated tap position, the allowable error is ±0.5%. For three-winding transformers, perform ratio tests for HV-MV, MV-LV separately.

5. Check Three-Phase Connection Group and Single-Phase Transformer Terminal Polarity

The verification results should match the design requirements, nameplate markings, and symbols on the transformer housing.

6. Insulation Oil Sampling and Testing

Oil sampling should only be performed after the transformer has been completely filled with oil and allowed to stand for the specified time. After collecting the oil sample, seal the container properly and promptly deliver it to the relevant department for testing.

7. Insulation Resistance, Absorption Ratio or Polarization Index Measurement

All insulation-related tests should be conducted after the insulating oil has passed inspection and during weather conditions with appropriate humidity levels. For transformers requiring polarization index measurement, verify that the short-circuit current of the insulation resistance meter is not less than 2mA. Record the ambient temperature during testing to facilitate comparison with factory values at equivalent temperatures. The measured values should not be less than 70% of factory values. Test items should include: HV-(MV+LV+ground), MV-(HV+LV+ground), LV-(MV+HV+ground), overall-ground, core-(clamp+ground), and clamp-(core+ground). For example, for HV-(MV+LV+ground), short-circuit all three phases of the high-voltage side and the corresponding neutral point (if present), ground all other parts, connect the high-voltage terminal of the insulation resistance meter to the HV side, and the ground terminal to ground for testing.

8. Measurement of Dissipation Factor (tanδ) for Windings with Bushings

Test using the reverse wiring method, following the instrument's specified wiring configuration. Test items include: HV-(MV+LV+ground), MV-(HV+LV+ground), LV-(MV+HV+ground), and overall-ground, performed sequentially. During testing, suspend the high-voltage test leads of the dissipation factor tester with insulating tape to prevent contact with the transformer tank. Record the ambient temperature during testing. When comparing with factory values at equivalent temperatures, the measured values should not exceed 1.3 times the factory values. If measurements deviate significantly from factory values, clean the bushings or use conductive shielding on the bushings to reduce surface leakage current. Testing should preferably be conducted during weather with relatively low humidity.

9. DC Leakage Current Measurement for Windings with Bushings

Leakage current measurement should preferably be taken at the high-voltage terminal. Test items include: HV-(MV+LV+ground), MV-(HV+LV+ground), LV-(MV+HV+ground). Testing should be conducted during weather with low humidity, and the ambient temperature should be recorded. The leakage current values must not exceed the specifications in the handover standards.

10. Electrical Tests

10.1 Winding Deformation Test

For transformers rated 35kV and below, the low-voltage short-circuit impedance method is recommended. For transformers rated 66kV and above, the frequency response analysis (FRA) method is recommended for measuring winding characteristic spectra.

10.2 AC Withstand Voltage Test

Perform AC withstand voltage tests at the transformer terminals using either externally applied power frequency voltage or induced voltage methods. When possible, use series resonance induced voltage testing to reduce the required test equipment capacity. For transformers rated 110kV and above, the neutral point should preferably undergo separate AC withstand voltage testing. Test voltage values should follow handover standards.

10.3 Long-Time Induced Voltage Test with Partial Discharge Measurement

For transformers rated 220kV and above, long-time induced voltage tests with partial discharge measurement must be performed on-site during new installation. For 110kV transformers, partial discharge testing is recommended when insulation quality is in doubt. These tests detect non-penetrating internal insulation defects in transformers.

10.4 Full-Voltage Impulse Closing Test at Rated Voltage

Perform according to startup plan requirements.

10.5 Phase Verification

Verify the transformer phase sequence, which must match the grid phase sequence.

Special attention should be paid to oil characteristics at negative temperatures for each oil system. For example, the oil inside the main tank has higher viscosity at negative temperatures, resulting in poor fluidity and heat dissipation. The oil in the on-load tap changer switching compartment at negative temperatures can prolong the switching process and increase the temperature rise of transition resistors.

For the main tank oil system of EHV oil-immersed transformers, attention should also be paid to oil flow electrification phenomena. Prevent the transition from oil flow electrification to oil flow discharge by controlling oil resistivity, oil flow velocity in various parts, and providing sufficient space for releasing electrical charges in the oil.

Give a tip and encourage the author!
Recommended
Purpose of Pre-Commissioning Impulse Testing for Power Transformers
No-Load Full-Voltage Switching Impulse Testing for Newly Commissioned TransformersFor newly commissioned transformers, besides conducting necessary tests according to handover test standards and protection/secondary system tests, no-load full-voltage switching impulse tests are typically performed before official energization.Why Perform Impulse Testing?1. Check for Insulation Weaknesses or Defects in the Transformer and Its CircuitWhen disconnecting a no-load transformer, switching overvoltages
12/23/2025
What are the classification types of power transformers and their applications in energy storage systems?
Power transformers are core primary equipment in power systems that realize electrical energy transmission and voltage conversion. Through the principle of electromagnetic induction, they convert AC power of one voltage level to another or multiple voltage levels. In the transmission and distribution process, they play a critical role in "step-up transmission and step-down distribution," while in energy storage systems, they perform voltage step-up and step-down functions, ensuring efficient pow
12/23/2025
Power transformers Insulation Resistance & Dielectric Loss Analysis
1 IntroductionPower transformers are among the most critical equipment in power systems, and it is essential to maximize prevention and minimize the occurrence of transformer failures and accidents. Insulation failures of various types account for more than 85% of all transformer accidents. Therefore, to ensure safe transformer operation, regular insulation testing of transformers is necessary to detect insulation defects in advance and promptly address potential accident hazards. Throughout my
12/22/2025
5 Fault Diagnosis Techniques for Large Power Transformers
Transformer Fault Diagnosis Methods1. Ratio Method for Dissolved Gas AnalysisFor most oil-immersed power transformers, certain combustible gases are produced in the transformer tank under thermal and electrical stress. The combustible gases dissolved in oil can be used to determine the thermal decomposition characteristics of the transformer oil-paper insulation system based on their specific gas content and ratios. This technology was first used for fault diagnosis in oil-immersed transformers.
12/20/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.