Impact Analysis of Voltage Transformer Installation on Line Side vs. Load Side of Power Inlet Circuit Breaker for (ATS)

James
07/03/2025

Automatic backup switching (ABTS) devices are core components ensuring the safe, reliable, and stable operation of factory power grids. Their startup logic strictly follows the dual criteria of "loss of voltage in the working power supply + no - current detection", effectively avoiding misjudgments caused by secondary disconnection of voltage transformers (VTs) or maloperations of ABTS due to secondary circuit faults of current transformers (CTs). The activation condition requires both "no voltage and no current" or "voltage/current values below the protection setting", with no exceptions.
ABTS relies on VTs to collect voltage signals and CTs to collect current signals. Thus, the installation positions of these transformers directly determine the accuracy of the device in judging the status of the working power supply. Among them, regardless of whether CTs are installed on the upper or lower side of the power inlet circuit breaker, ABTS can accurately identify "circuit breaker current - carrying status and busbar load - carrying conditions"; however, there are significant differences in how ABTS judges the live status of busbars when VTs are installed on the upper side (inlet side) versus the lower side (busbar side) of the circuit breaker, which requires focused analysis. The system wiring is shown in Figure 1.
1. Voltage Transformer Installed on the Upper Side of the Power Inlet Circuit Breaker (Inlet VT)
(1) Normal Operation of the Inlet Power Supply
When ABTS takes power from the line voltage transformer TV1, if circuit breaker 1DL is in the "working position + closed state", TV1 collects the inlet voltage, which is equivalent to the busbar voltage. ABTS then determines that Section I busbar is live.
(2) Loss of Inlet Power Supply
When the inlet power supply fails, TV1 collects a voltage of zero and the CT collects a current of zero, triggering ABTS to act: first trip 1DL, then close bus - tie circuit breaker 3DL, restoring power to Section I busbar and allowing the load to continue operating.
(3) Maloperation of the Circuit Breaker (Core Hidden Risk Scenario)
If 1DL switches from the closed to the open position due to misoperation or mechanical failure, Section I busbar loses power and the load shuts down. The CT collects a current of zero, but TV1 still collects the normal inlet - side voltage (not dropping to the protection setting), so ABTS fails to detect "busbar voltage loss" and cannot start. 3DL cannot close, causing prolonged power loss on Section I busbar and severe production interruptions.
(4) Logic Optimization Solution
Precise identification requires implementing a "circuit breaker position interlock + voltage criterion": TV1 - collected voltage is equivalent to the busbar voltage only when 1DL is in the "working position + closed state"; if the circuit breaker position is abnormal (non - working position/open state), ABTS forcibly judges the busbar voltage as 0. Additionally, a "circuit breaker position verification" logic must be added: after detecting busbar voltage loss, ABTS verifies the status of 1DL before deciding to "trip 1DL + close 3DL" or directly "close 3DL".
2. Voltage Transformer Installed on the Lower Side of the Power Inlet Circuit Breaker (Busbar VT)
When ABTS takes power from the busbar voltage transformer TV3, if circuit breaker 1DL is in the "working position + closed state", TV3 directly collects the voltage of Section I busbar, and ABTS obtains the actual busbar voltage signal.
(1) Loss of Inlet Power Supply
When the inlet power supply fails or 1DL maloperates to the open position, TV3 collects a voltage of zero and the CT collects a current of zero, triggering ABTS to act:
  • If the inlet power supply fails: trip 1DL → close 3DL to restore busbar power;
  • If the circuit breaker maloperates: directly close 3DL to restore busbar power, with no load interruption.
(2) Advantage Analysis
The busbar VT can "realtime and directly reflect the busbar live status" without relying on circuit breaker position criteria. ABTS has a simpler action logic, accurately identifying busbar voltage loss scenarios and avoiding misoperation/non - operation risks.
3. Comparative Analysis of the Two Installation Schemes
(1) Complexity of Action Logic
  • Inlet - side installation (TV1): Requires adding "circuit breaker position verification + voltage conversion logic", increasing the difficulty of ABTS action judgment;
  • Busbar - side installation (TV3): Directly collects busbar voltage with clear logic and high action reliability.
(2) Potential Risks (Major Hidden Danger of Inlet - Side Installation)
If TV1 on the inlet side is paralleled with line L1, when L1 loses power, ABTS triggers the "trip 1DL → close 3DL" action. The busbar voltage is then reverse - fed to L1 through TV1, causing a "voltage reverse charging accident": at best, tripping the air circuit breaker on the L1 side and causing secondary voltage loss; at worst, damaging equipment and even triggering personal electric shock risks.
4. Conclusion and Recommendations
To ensure ABTS "acts accurately and reliably" during busbar voltage loss and avoid voltage reverse charging accidents when VTs are paralleled, VTs should be installed on the lower side (busbar side) of the power inlet circuit breaker to directly collect busbar voltage via the busbar VT. This enables realtime reflection of the actual busbar status, providing reliable criteria for ABTS. It ensures the device acts quickly and accurately during busbar voltage loss, minimizing impacts on production and daily life.
James

Professionalism builds strength. As an expert in the installation and operation of electrical equipment, I am proficient in the installation process and strictly adhere to standards. I skillfully master the operation essentials and can swiftly eliminate faults. With a heart that constantly explores new knowledge, I illuminate the path to the efficient operation of electrical equipment.

Selection and Application of Small Reactors at the Neutral Point of 500kV Substations
Selection and Application of Small Reactors at the Neutral Point of 500kV Substations
1 Relevant Theories of Small Neutral Point Reactors in 500kV Substations1.1 Definitions and RolesA reactor is a key power system component that controls the phase relationship between AC current and voltage, divided into inductive and capacitive types. Inductive reactors limit short-circuit currents and improve stability; capacitive ones enhance transmission efficiency and voltage quality. A small neutral point reactor is a specialized type connected between a three-phase system's neutral point
Echo
07/25/2025
What are the comprehensive considerations for product selection and installation?
What are the comprehensive considerations for product selection and installation?
In real-world engineering projects, selecting and installing 35kV combined instrument transformers isn't just a matter of "buying and installing" — it requires a comprehensive evaluation of many factors, such as environmental conditions, equipment performance, and maintenance convenience. Only by taking all these aspects into account can we ensure that the equipment runs safely and stably for a long time under specific conditions.1. Oil-Immersed vs. Dry-Type Transformers — Which One
James
07/22/2025
What aspects should be considered when selecting and installing 35kV combined transformers?
What aspects should be considered when selecting and installing 35kV combined transformers?
The installation quality of combined instrument transformers directly affects whether they can operate safely and stably. Therefore, during the installation process, several key aspects must not be overlooked — such as foundation construction, grounding, sealing checks, testing and commissioning, as well as secondary wiring. Below, I’ll explain these points in a more conversational way.1. Foundation Construction Must Be Solid, Especially in Plateau AreasAlthough a combined instrument
James
07/22/2025
A Quick Verification Method for Low-Voltage Current Transformers
A Quick Verification Method for Low-Voltage Current Transformers
1. Selection of Low - Voltage Current Transformer ConfigurationThere are many factors leading to wrong selection of low - voltage current transformers in civil construction projects. For example, common factors include design problems: the calculated coefficient designed for the load of electrical equipment is relatively large, or the transformation ratio of the current transformer is selected incorrectly. Such a series of reasons will affect the use of electrical equipment. Therefore, in the co
James
07/16/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!