Vector Group Test of Power Transformer

Encyclopedia
Encyclopedia
Field: Encyclopedia
0
China

Vector Group Test Definition


The vector group test of a transformer checks the phase sequence and angular difference to ensure transformers can operate in parallel.


Vector Group Test of Transformer


The vector group of a transformer is essential for successful parallel operation of transformers. Every electrical power transformer must undergo a vector group test at the factory to ensure it matches the customer’s specified vector group.


The phase sequence, or the order in which phases reach their peak voltage, must be identical for transformers operating in parallel. Otherwise, each pair of phases will short circuit during the cycle.


The several secondary connections are available in respect of various primary three phase connection in a the three phase transformer. So for same primary applied three phase voltage there may be different three phase secondary voltages with various magnitudes and phases for different internal connection of the transformer.


Let’s have a discussion in detail by example for better understanding.


We know that, the primary and secondary coils on any one limb have induced emfs that are in time-phase. Let’s consider two transformers of same number primary turns and the primary windings are connected in star.


The secondary number of turns per phase in both transformers are also same. But the first transformer has star connected secondary and other transformer has delta connected secondary. If same voltages are applied in primary of both transformers, the secondary induced emf in each phase will be in same time-phase with that of respective primary phase, as because the the primary and secondary coils of same phase are wound on the same limb in the core of transformer. 


In first transformer, as the secondary is star connected, the secondary line voltage is √3 times of induced voltage per secondary phase coil. But in case of second transformer, where secondary is delta connected, the line voltage is equal to induced voltage per secondary phase coil. If we go through the vector diagram of secondary line voltages of both transformer, we will easily find that there will be a clear 30o angular difference between the line voltages of these transformers.


If we try to run these transformers in parallel, a circulating current will flow between them due to the phase angle difference between their secondary line voltages. This phase difference cannot be compensated. Therefore, transformers with secondary voltage phase displacements cannot be used for parallel operation of transformers.


The following table shows connections where transformers can operate in parallel, considering phase sequence and angular differences. Based on their vector relation, three-phase transformers are divided into different vector groups. Transformers within the same vector group can be easily paralleled if they meet other conditions for parallel operation.


09b8d6f4edfa5d826217bd0753f15e3c.jpeg

27893049a08bc4f823475703cdf686cd.jpeg5152ab7ee8a4f9b621d24f5ce02588a5.jpeg 3a928bd77616d347c22865a1e7985d4a.jpeg



Procedure of Vector Group Test of Transformer


Let’s have a YNd11 transformer.


  • Connect neutral point of star connected winding with earth.



  • Join 1U of HV and 2W of LV together.



  • Apply 415 V, three phase supply to HV terminals.



  • Measure voltages between terminals 2U-1N, 2V-1N, 2W-1N, that means voltages between each LV terminal and HV neutral.


  • Also measure voltages between terminals 2V-1V, 2W-1W and 2V-1W.

 

c389299b9c46b6375a6feb7e8107a0cb.jpeg

 

For YNd11 transformer, we will find,

2U-1N > 2V-1N > 2W-1N

2V-1W > 2V-1V or 2W-1W .

The vector group test of transformer for other group can also be done in similar way.

Give a tip and encourage the author!
Recommended
THD Measurement Error Standards for Power Systems
THD Measurement Error Standards for Power Systems
Error Tolerance of Total Harmonic Distortion (THD): A Comprehensive Analysis Based on Application Scenarios, Equipment Accuracy, and Industry StandardsThe acceptable error range for Total Harmonic Distortion (THD) must be evaluated based on specific application contexts, measurement equipment accuracy, and applicable industry standards. Below is a detailed analysis of key performance indicators in power systems, industrial equipment, and general measurement applications.1. Harmonic Error Standar
Edwiin
11/03/2025
How Vacuum Tech Replaces SF6 in Modern Ring Main Units
How Vacuum Tech Replaces SF6 in Modern Ring Main Units
Ring main units (RMUs) are used in secondary power distribution, directly connecting to end-users such as residential communities, construction sites, commercial buildings, highways, etc.In a residential substation, the RMU introduces 12 kV medium voltage, which is then stepped down to 380 V low voltage through transformers. The low-voltage switchgear distributes electrical energy to various user units. For a 1250 kVA distribution transformer in a residential community, the medium-voltage ring m
James
11/03/2025
Why Monitoring Accuracy Matters in Power Quality Systems
Why Monitoring Accuracy Matters in Power Quality Systems
The Critical Role of Monitoring Accuracy in Power Quality Online DevicesThe measurement accuracy of online power quality monitoring devices is the core of the power system’s “perception capability,” directly determining the safety, economy, stability, and reliability of power supply to users. Inadequate accuracy leads to misjudgment, incorrect control, and flawed decision-making—potentially causing equipment damage, economic losses, or even grid failures. Conversely, high accuracy enables precis
Oliver Watts
10/30/2025
How Does Power Dispatching Ensure Grid Stability and Efficiency?
How Does Power Dispatching Ensure Grid Stability and Efficiency?
Electric Power Dispatching in Modern Power SystemsThe power system is a critical infrastructure of modern society, providing essential electrical energy for industrial, commercial, and residential use. As the core of power system operation and management, electric power dispatching aims to meet electricity demand while ensuring grid stability and economic efficiency.1. Basic Principles of Electric Power DispatchingThe fundamental principle of power dispatching is to balance supply and demand by
Echo
10/30/2025
Related Products
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.