• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Induced Voltage Test Issues and Solutions for HKSSPZ-6300/110 Arc Furnace Transformer

Oliver Watts
Oliver Watts
Field: Inspection and testing
China

A HKSSPZ-6300/110 electric arc furnace transformer has the following basic parameters:

Rated capacity S = 6300 kVA, primary voltage U₁ = 110 kV, secondary voltage U₂ = 110–160 V, vector group YNd11, with both low-voltage winding ends (start and finish) brought out, and equipped with 13-step on-load tap changing. Insulation levels: HV/HV neutral/LV, LI480AC200 / LI325AC140 / AC5.

The transformer uses a dual-core series voltage regulation design, with an "8"-shaped low-voltage winding configuration. The schematic for the induced voltage test is shown in Figure 1.

Test conditions: tap changer set at position 13; 10 kV applied to tertiary windings Am, Bm, Cm; with K = 2, only phase A is illustrated (phases B and C are identical). Calculated values: UZA = K × 10 = 20 kV, UG₀ = K × 110 / √3 ≈ 63.509 kV, UGA = 3 × 63.509 = 190.5 kV (95% of rated), UAB = 190.5 kV, frequency = 200 Hz.

After completing the test connections per the diagram, the induced voltage test began. When UZA was raised to 4000–5000 V, distinct "crackling" corona discharge sounds were observed near the low-voltage terminal bushings, accompanied by the odor of ozone. Simultaneously, the partial discharge (PD) detector indicated PD levels exceeding 1400 pC. However, the measured voltage between low-voltage terminals remained correct. Initially, we suspected potential issues with the low-voltage terminal material or the effect of the 200 Hz test frequency on the resin terminal. In a second test using a 50 Hz power source at the same voltage (4000–5000 V), the same phenomena were observed, thereby ruling out the influence of the 200 Hz frequency.

We then carefully reviewed the test circuit diagram and actual connections. It was noted that the low-voltage winding ends (start and finish) are both externally brought out and are normally connected externally into delta or star configuration when connected to the furnace. During the induced voltage test, however, the low-voltage terminals were neither connected in star nor in delta, nor grounded—leaving them in a floating potential state. Could this floating potential be the cause?

To test this hypothesis, we temporarily connected the x, y, and z terminals together and reliably grounded them before re-running the test. The aforementioned discharge phenomena disappeared completely. When the voltage was increased to 1.5 times the level, PD was only about 20 pC. The test voltage was further increased to 2 times, and the transformer successfully passed the induced voltage withstand test.

Conclusion: For this type of dual-core series voltage-regulated furnace transformer with both low-voltage winding ends brought out, although the voltage between terminals (e.g., a and x) is low, the absence of a reliable ground connection can create a floating potential, leading to the observed partial discharge. Therefore, during induced voltage testing, the x, y, and z terminals should be shorted together and reliably grounded to eliminate such anomalies.

Give a tip and encourage the author!
Recommended
How to Test Vacuum in Vacuum Circuit Breakers
How to Test Vacuum in Vacuum Circuit Breakers
Vacuum Integrity Testing of Circuit Breakers: A Critical Measure for Performance EvaluationVacuum integrity testing is a key method for assessing the vacuum performance of circuit breakers. This test effectively evaluates the insulation and arc-quenching capabilities of the breaker.Before testing, ensure the circuit breaker is properly installed and correctly connected. Common vacuum measurement methods include the high-frequency method and the magnetic control discharge method. The high-frequen
Oliver Watts
10/16/2025
Ensure Hybrid System Reliability with Full Production Testing
Ensure Hybrid System Reliability with Full Production Testing
Production Testing Procedures and Methods for Wind-Solar Hybrid SystemsTo ensure the reliability and quality of wind-solar hybrid systems, several critical tests must be conducted during production. Wind turbine testing primarily includes output characteristic testing, electrical safety testing, and environmental adaptability testing. Output characteristic testing requires measuring voltage, current, and power under varying wind speeds, plotting wind-power curves, and calculating power generatio
Oliver Watts
10/15/2025
Electrical Meter Accuracy Issues? Solutions Revealed
Electrical Meter Accuracy Issues? Solutions Revealed
Analysis of Measurement Errors in Electrical Instruments and Elimination Strategies1.Electrical Instruments and Common Testing MethodsElectrical instruments play a vital role in the generation, transmission, and utilization of electricity. As a special form of energy, electricity requires strict safety standards in production and use. Safe electricity usage is crucial to daily life, production, and socio-economic development. Power system monitoring relies on electrical instruments, which are of
Oliver Watts
10/07/2025
High-Voltage Electrical Testing: Key Safety Requirements for Field Operations
High-Voltage Electrical Testing: Key Safety Requirements for Field Operations
The test site layout must be reasonable and organized. High-voltage testing equipment should be placed close to the test object, live parts must be isolated from each other, and remain within the clear line of sight of test personnel. Operational procedures must be rigorous and systematic. Unless otherwise specified, voltage must not be suddenly applied or removed during operation. In case of abnormal conditions, voltage increase must be stopped immediately, pressure rapidly reduced, power disc
Oliver Watts
09/23/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.