• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Constant testing of high-voltage cable lines

Oliver Watts
Oliver Watts
Field: Inspection and testing
China

1. Definition of High-Voltage Cable Line Constant Testing

High-voltage cable line constant testing refers to the systematic measurement, using specialized instruments, of electrical parameters such as resistance, inductance, capacitance, and conductance before a cable line is commissioned or after major maintenance. The aim is to obtain fundamental data characterizing the electromagnetic properties of the cable, serving as a critical testing phase that provides accurate parameter support for power system load flow calculations, relay protection configuration, short-circuit current analysis, and cable operational status evaluation.

Its core value lies in two aspects: first, verifying deviations between design values and actual measured values to avoid protection malfunctions or system stability issues caused by parameter mismatches; second, establishing a "baseline parameter database" for the cable line, providing a reference for identifying subsequent operational changes (such as insulation aging or poor joint contact). According to DL/T 596 "Preventive Test Regulations for Electrical Equipment" and GB 50217 "Design Standard for Power Engineering Cables," all constant tests must be completed for 220 kV and above cable lines during commissioning, while 110 kV and below lines may be selectively implemented based on system importance.

2. Complete Process of High-Voltage Cable Line Constant Testing

2.1 Pre-Test Preparation Phase

2.1.1 Collection of Technical Data and Site Survey
Comprehensive cable line design parameters must be obtained, including voltage level (e.g., 220 kV, 500 kV), cable model (e.g., YJV22-220 kV-1×2500 mm²), installation method (direct burial, conduit, cable tray), length (accurate to 0.1 km), conductor material (copper or aluminum), insulation type (XLPE, oil-impregnated paper), metallic shield structure (copper tape, copper wire), and grounding method (direct grounding, cross-bonded grounding). A site survey must confirm communication conditions at the main test site (typically a cable terminal station) and auxiliary site (opposite substation), integrity of the grounding system, safe distance from nearby energized equipment (≥1.5 times the safety distance corresponding to the test voltage), and use an electrostatic voltmeter to measure induced voltage (which may reach tens of volts on cables near energized lines, requiring anti-electrocution measures).

2.1.2 Test Plan Development and Equipment Selection

Based on the "Guidelines for Cable Line Parameter Testing," a detailed plan including test items (positive-sequence resistance, zero-sequence capacitance, etc.), instrument models, wiring methods, and safety measures must be developed. Core equipment includes:

  • Line parameter tester (accuracy class 0.2, frequency range 45–65 Hz, output current ≥10 A);

  • Three-phase voltage regulator (capacity ≥5 kVA, adjustable range 0–400 V);

  • Isolation transformer (1:1 ratio to prevent grid interference);

  • Auxiliary tools: thermometer/hygrometer (ambient temperature and humidity must be recorded for temperature correction of parameters), discharge rod (25 kV class, discharge time ≥5 min), shorting wires (cross-sectional area ≥25 mm² copper cable, length customized on-site), and insulating pole (3 m, insulation resistance ≥1000 MΩ).

2.1.3 Safety Measures Deployment

    The test area must be enclosed with safety barriers and marked with "High Voltage Danger" warning signs. Both the main and auxiliary test sites must be equipped with walkie-talkies (communication range ≥1 km) and emergency stop buttons. All test personnel must wear insulating gloves (35 kV class), insulating shoes (breakdown voltage ≥15 kV), and double-hook safety harnesses when working at height. The far end of the cable must be disconnected from other equipment and fitted with temporary grounding wires to prevent back-feeding.

2.2 On-Site Testing Implementation Phase

2.2.1Test Wiring and Phase Verification
Taking positive-sequence parameter testing as an example, the wiring procedure is as follows:
(1) Short-circuit and ground the three-phase conductors (A, B, C) at the far end; ground the metallic shield at one end only (for cross-bonded systems, disconnect the bonding links in the cross-bonding box and test each section separately);
(2) Apply AC voltage (typically 380 V) to phase A at the main test end via a voltage regulator and isolation transformer; leave phases B and C open; connect the voltage and current sampling leads of the line parameter tester.
Phase verification: Use a multimeter to measure the voltage phase of each phase to ensure correct same-name phase connections and avoid measurement errors due to incorrect phase sequence.

2.2.2Parameter Measurement Procedure
Positive-sequence resistance (R1) and reactance (X1): Apply test current (typically 5–10 A) to phase A, measure the magnitude and phase angle difference between voltage and current, and calculate using the formulas R1 = U/I·cosϕ and X1 = U/I·sinϕ. Repeat the test three times and take the average value, with at least a 1-minute interval between tests to prevent conductor heating from affecting resistance values.
Zero-sequence capacitance (C0): Short-circuit and connect phases A, B, and C to the high-voltage terminal of the tester, ground the metallic shield, apply 100 V, and measure capacitance using the Schering bridge principle. Linearity must be verified at different voltage levels (50 V, 100 V, 200 V), with deviations ≤2%.
Insulation resistance (Rins): Use a 2500 V megohmmeter to measure insulation resistance between conductor and shield. Record the reading after 1 minute of applied voltage and simultaneously record ambient temperature. Convert to the 20°C reference value using the formula R20 = Rt × 10^(0.004(t−20)) (where t is the measured temperature).

2.2.3Data Recording and Validity Assessment
Immediately after completing each parameter test, record the instrument reading, ambient temperature and humidity, test time, and any anomalies (e.g., voltage fluctuations, unusual noises). Data validity criteria include:

  • Relative deviation of three repeated measurements of the same parameter ≤5%;

  • Deviation of positive-sequence impedance from design value ≤10% (accounting for installation length error);

  • Insulation resistance, after temperature correction, should be ≥1000 MΩ·km (standard for XLPE cables).

High-Voltage Cable Test.jpg

2.3 Post-Test Processing Phase

2.3.1 Safe Discharge and Wiring Removal
After testing, first disconnect the power supply to the voltage regulator. Then, use a discharge rod to perform "multiple discharges" on the cable conductor and shield (each discharge lasting ≥1 minute, with a 30-second interval). Only after confirming the residual voltage is ≤50 V should the shorting wires and test leads be removed. For cross-bonded systems, reconnect the bonding links in the cross-bonding box and measure continuity to ensure proper connection.

2.3.2 Data Correction and Report Preparation
According to GB/T 3048.4 "Methods for Electrical Testing of Electric Wires and Cables," measured parameters must be corrected for temperature and frequency:
Resistance temperature correction:
For copper conductors: R₂₀ = Rₜ / [1 + α(t − 20)] (where α = 0.00393/°C);
Capacitance frequency correction:
When the test frequency deviates from 50 Hz, correct using: C₅₀ = Cf × (1 + 0.002∣f − 50∣).
The test report must include the testing standard (e.g., DL/T 475), instrument calibration certificate number, a parameter comparison table (design values vs. measured values), and a conclusive assessment (e.g., "Pass", "Retest Recommended").

Give a tip and encourage the author!
Recommended
How to Test Vacuum in Vacuum Circuit Breakers
How to Test Vacuum in Vacuum Circuit Breakers
Vacuum Integrity Testing of Circuit Breakers: A Critical Measure for Performance EvaluationVacuum integrity testing is a key method for assessing the vacuum performance of circuit breakers. This test effectively evaluates the insulation and arc-quenching capabilities of the breaker.Before testing, ensure the circuit breaker is properly installed and correctly connected. Common vacuum measurement methods include the high-frequency method and the magnetic control discharge method. The high-frequen
Oliver Watts
10/16/2025
Ensure Hybrid System Reliability with Full Production Testing
Ensure Hybrid System Reliability with Full Production Testing
Production Testing Procedures and Methods for Wind-Solar Hybrid SystemsTo ensure the reliability and quality of wind-solar hybrid systems, several critical tests must be conducted during production. Wind turbine testing primarily includes output characteristic testing, electrical safety testing, and environmental adaptability testing. Output characteristic testing requires measuring voltage, current, and power under varying wind speeds, plotting wind-power curves, and calculating power generatio
Oliver Watts
10/15/2025
Electrical Meter Accuracy Issues? Solutions Revealed
Electrical Meter Accuracy Issues? Solutions Revealed
Analysis of Measurement Errors in Electrical Instruments and Elimination Strategies1.Electrical Instruments and Common Testing MethodsElectrical instruments play a vital role in the generation, transmission, and utilization of electricity. As a special form of energy, electricity requires strict safety standards in production and use. Safe electricity usage is crucial to daily life, production, and socio-economic development. Power system monitoring relies on electrical instruments, which are of
Oliver Watts
10/07/2025
High-Voltage Electrical Testing: Key Safety Requirements for Field Operations
High-Voltage Electrical Testing: Key Safety Requirements for Field Operations
The test site layout must be reasonable and organized. High-voltage testing equipment should be placed close to the test object, live parts must be isolated from each other, and remain within the clear line of sight of test personnel. Operational procedures must be rigorous and systematic. Unless otherwise specified, voltage must not be suddenly applied or removed during operation. In case of abnormal conditions, voltage increase must be stopped immediately, pressure rapidly reduced, power disc
Oliver Watts
09/23/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.