Analysis of the Meaning of 5P20 in Current Transformers

Explanation of Accuracy Grade

In current transformers (CTs), 5P20 is an identifier that represents its performance characteristics. This identifier consists of three parts: Accuracy Class, Protection Class, and Accuracy Limit Factor.

  • Accuracy Class (5): The number 5 represents the accuracy class of this current transformer. The accuracy class reflects the measurement error of the current transformer under specific conditions. A smaller number indicates higher accuracy. Accuracy class 5 is typically used for applications that do not require high precision, such as monitoring or protection, where small errors in measurement are acceptable.

  • Protection Grade (P): The letter P denotes that this is a current transformer for protection purposes. Protection grade current transformers are designed to carry fault currents and maintain their accuracy under fault conditions.

  • Accuracy Limit Factor (20): The number 20 represents the Accuracy Limit Factor (ALF) of the current transformer. This factor indicates the magnitude of the fault current that can safely flow through the primary winding of the CT without causing it to saturate. In this case, it means that when the primary current reaches 20 times the rated current due to a short circuit, the composite error of the transformer is less than 5%.

Practical Application

Current transformers of the 5P20 type are typically used in applications that can accept lower levels of accuracy, such as some general-purpose monitoring or control systems. While they may not be suitable for applications requiring high precision current measurements, in many cases, they offer sufficient performance and remain a popular choice due to their cost-effectiveness and reliability.

Summary

In summary, 5P20 denotes a protective class current transformer with an accuracy class of 5, capable of maintaining a total error within 5% when the primary current is up to 20 times its rated current. This characteristic makes it widely applicable in various protection and monitoring applications.

Encyclopedia

The Electricity Encyclopedia is dedicated to accelerating the dissemination and application of electricity knowledge and adding impetus to the development and innovation of the electricity industry.

Cost Differences and Performance Comparison of 35kV New Energy Transformers Based on Dry-Type, Mineral Oil, and Vegetable Oil
Cost Differences and Performance Comparison of 35kV New Energy Transformers Based on Dry-Type, Mineral Oil, and Vegetable Oil
For users, when purchasing a 35kV new energy transformer, choosing between dry-type, mineral oil-filled, or vegetable oil-filled types involves multiple considerations. These include user habits, maintenance-free performance, safety and fire resistance, volume and weight, among others. However, cost differences are undoubtedly one of the most crucial factors.To illustrate the issue intuitively, this paper selects a three-level energy efficiency dual-winding new energy transformer with a rated ca
Ron
07/26/2025
What is the connection group of a transformer?
What is the connection group of a transformer?
Transformer Connection GroupThe connection group of a transformer refers to the phase difference between the primary and secondary voltages or currents. It is determined by the winding directions of the primary and secondary coils, the labeling of their start and end terminals, and the connection mode. Expressed in a clock-like format, there are 12 groups in total, numbered from 0 to 11.The DC method is commonly used to measure the transformer's connection group, mainly to verify whether the con
Vziman
07/26/2025
What is the sequence for powering down the transformer?
What is the sequence for powering down the transformer?
The sequence for shutting down a main transformer is as follows: when de-energizing, the load side should be shut down first, followed by the power supply side. For energizing operations, the reverse order applies: the power supply side is energized first, then the load side. This is because: Energizing from the power supply side to the load side makes it easier to identify the fault range and take prompt judgment and handling measures in case of a fault, preventing the fault from spreading or e
Rockwell
07/26/2025
What are the methods for switching operations of station transformers?
What are the methods for switching operations of station transformers?
Let's take an auxiliary power system with two station transformers as an example. When one station transformer needs to be out of service, there are two operation methods: non-interruptive power supply and instantaneous power interruption. Generally, the method of instantaneous power interruption on the low-voltage side is preferred.The operation method for instantaneous power interruption on the low-voltage side is as follows:Open the 380V power incoming circuit breaker of the corresponding sec
Vziman
07/26/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!