When using a megohmmeter to test the insulation resistance of a power transformer, the following safety measures should be followed:

54044e3a-8917-4c6c-ac5f-9fa4da1c4b6f.jpg

I. Preparation before testing

Understand equipment information

Before conducting the test, obtain detailed information about the specifications, parameters, and operating status of the power transformer to be tested. Familiarize yourself with information such as the rated voltage and capacity of the transformer so as to correctly select the test voltage level of the megohmmeter. For example, for a transformer with a rated voltage of 10 kV, a megohmmeter with a test voltage of 2500 V is usually selected for testing.

Consult the historical test records and maintenance files of the transformer to understand its previous insulation status and provide a reference for this test.

Check the megohmmeter

Ensure that the megohmmeter is in good working condition. Check whether the appearance of the megohmmeter is damaged, whether the pointer is flexible, and whether the wiring is firm. For example, check whether the case has cracks, whether the pointer can swing freely, and whether the test leads are damaged.

Before use, perform open-circuit and short-circuit tests on the megohmmeter to verify its performance. Separate the two test terminals of the megohmmeter, turn the handle, and observe whether the pointer points to infinity; then short-circuit the two test terminals and turn the handle. The pointer should point to zero.

Take safety precautions

Test personnel should wear personal protective equipment such as insulating gloves, insulating shoes, and safety helmets. These protective equipments can effectively prevent electric shock accidents. For example, insulating gloves should meet the requirements of the corresponding voltage level, and insulating shoes should have good insulation performance.

Set up warning signs at the test site to prevent unrelated personnel from entering the test area. Warning signs should be conspicuous and clear, such as "High voltage danger, keep away."

II. Safety measures during testing

Correct wiring

Connect the test leads correctly according to the instructions of the megohmmeter. Usually, connect the "L" terminal of the megohmmeter to the winding of the transformer and the "E" terminal to the grounding end of the transformer. For example, for a three-phase transformer, each phase winding can be tested separately to ensure firm and reliable wiring.

During the wiring process, maintain good contact between the test leads and the transformer winding and grounding end to avoid inaccurate test results or arcing due to poor contact.

Slow voltage rise

When turning the handle, slowly and evenly increase the output voltage of the megohmmeter to avoid sudden voltage rise causing impact on the transformer insulation. For example, you can first turn the handle at a slower speed, observe the change of the pointer of the megohmmeter, and then gradually increase the speed of turning the handle after the pointer is stable.

During the voltage rise process, closely observe the pointer change of the megohmmeter and the operating status of the transformer. If the pointer swings violently, the transformer makes abnormal sounds or smokes, etc., stop the test immediately and take corresponding safety measures.

Prevent electric shock

During the test, the test personnel should maintain a sufficient safe distance from the transformer to avoid contacting the live parts of the transformer. For example, for a high-voltage transformer, the test personnel should stand outside a safe distance of at least 1.5 meters.

It is strictly prohibited to touch the test terminals of the megohmmeter and the winding of the transformer during the test to prevent electric shock accidents. If it is necessary to replace the test leads or adjust the test position, first reduce the output voltage of the megohmmeter to zero and then operate.

III. Safety measures after testing

Safe discharge

After the test is completed, first reduce the output voltage of the megohmmeter to zero, and then perform safe discharge on the transformer. During discharge, a special discharge rod or grounding wire can be used to short-circuit the winding of the transformer and the grounding end to slowly release the residual charge in the winding. For example, connect one end of the discharge rod to the winding of the transformer and the other end to the ground, and then gradually approach the grounding end to release the charge slowly.

The discharge process should last for a period of time to ensure that the charge in the transformer winding is completely released. Generally, the discharge time is not less than 2 minutes.

Organize equipment

Remove the test leads, organize the megohmmeter and test equipment, and store them in a dry and ventilated place. Check whether the test leads are damaged. If damaged, replace them in time.

Record and analyze the test results, compare the test data with historical data, and judge whether the insulation status of the transformer is good. If it is found that the insulation resistance value is significantly reduced or there are other abnormal conditions, report it in time and take corresponding maintenance measures.


Give a tip and encourage the author!
Recommended
THD Measurement Error Standards for Power Systems
THD Measurement Error Standards for Power Systems
Error Tolerance of Total Harmonic Distortion (THD): A Comprehensive Analysis Based on Application Scenarios, Equipment Accuracy, and Industry StandardsThe acceptable error range for Total Harmonic Distortion (THD) must be evaluated based on specific application contexts, measurement equipment accuracy, and applicable industry standards. Below is a detailed analysis of key performance indicators in power systems, industrial equipment, and general measurement applications.1. Harmonic Error Standar
Edwiin
11/03/2025
How Vacuum Tech Replaces SF6 in Modern Ring Main Units
How Vacuum Tech Replaces SF6 in Modern Ring Main Units
Ring main units (RMUs) are used in secondary power distribution, directly connecting to end-users such as residential communities, construction sites, commercial buildings, highways, etc.In a residential substation, the RMU introduces 12 kV medium voltage, which is then stepped down to 380 V low voltage through transformers. The low-voltage switchgear distributes electrical energy to various user units. For a 1250 kVA distribution transformer in a residential community, the medium-voltage ring m
James
11/03/2025
Why Monitoring Accuracy Matters in Power Quality Systems
Why Monitoring Accuracy Matters in Power Quality Systems
The Critical Role of Monitoring Accuracy in Power Quality Online DevicesThe measurement accuracy of online power quality monitoring devices is the core of the power system’s “perception capability,” directly determining the safety, economy, stability, and reliability of power supply to users. Inadequate accuracy leads to misjudgment, incorrect control, and flawed decision-making—potentially causing equipment damage, economic losses, or even grid failures. Conversely, high accuracy enables precis
Oliver Watts
10/30/2025
How Does Power Dispatching Ensure Grid Stability and Efficiency?
How Does Power Dispatching Ensure Grid Stability and Efficiency?
Electric Power Dispatching in Modern Power SystemsThe power system is a critical infrastructure of modern society, providing essential electrical energy for industrial, commercial, and residential use. As the core of power system operation and management, electric power dispatching aims to meet electricity demand while ensuring grid stability and economic efficiency.1. Basic Principles of Electric Power DispatchingThe fundamental principle of power dispatching is to balance supply and demand by
Echo
10/30/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.