High speed earthing switch (HSGS) rated operating sequence according to IEC standard (for>550kv)

Edwiin
Edwiin
Field: Power switch
China

High - Speed Earth Switches (HSES) have two rated operating sequences:

  • C–ti1–O

  • C–ti1–O–ti2–C–ti1–O

where:

  • ti1 represents a time period that is longer than the time needed for secondary arc extinction and for the dielectric recovery of air insulation at the fault location. ti1 is determined by users while taking system stability into account. The recommended value of ti1 is 0.15 s.

  • ti2 is the intermediate time specified by the system protection. ti2 encompasses the closing time of the circuit breakers after the HSES open, the duration of a new line fault, and the breaking time of the circuit breakers. After this ti2 period, the HSES can be reclosed. The recommended value of ti2 is 0.5 s. In this situation, the HSES should be capable of operating without any intentional time delay.

The figure depicts the time chart for the rated operating sequence of C–ti1–O–ti2–C–ti1–O with a circuit breaker (CB) in the grid.

In the figure:

  • Energizing of the closing circuit of the HSESs

  • Current start in HSESs

  • Contact touch of HSESs

  • Energizing of the opening release of the HSESs

  • Contact separation of HSESs

  • Arc extinction in HSESs

  • Fully open position of HSESs

The closing time of the HSES is typically less than 0.2 s.

Give a tip and encourage the author!
Recommended
What are the causes of failures in low-voltage switchgear circuit breakers themselves?
What are the causes of failures in low-voltage switchgear circuit breakers themselves?
Based on years of field statistics on switchgear accidents, combined with analysis focusing on the circuit breaker itself, the main causes have been identified as: failure of operation mechanism; insulation faults; poor breaking and closing performance; and poor conductivity.1.Failure of Operation MechanismFailure of operation mechanism manifests as delayed operation or unintended operation. Since the most basic and important function of a high-voltage circuit breaker is to operate correctly and
Felix Spark
11/04/2025
THD Measurement Error Standards for Power Systems
THD Measurement Error Standards for Power Systems
Error Tolerance of Total Harmonic Distortion (THD): A Comprehensive Analysis Based on Application Scenarios, Equipment Accuracy, and Industry StandardsThe acceptable error range for Total Harmonic Distortion (THD) must be evaluated based on specific application contexts, measurement equipment accuracy, and applicable industry standards. Below is a detailed analysis of key performance indicators in power systems, industrial equipment, and general measurement applications.1. Harmonic Error Standar
Edwiin
11/03/2025
Compact Air-Insulated RMUs for Retrofit & New Substations
Compact Air-Insulated RMUs for Retrofit & New Substations
Air-insulated ring main units (RMUs) are defined in contrast to compact gas-insulated RMUs. Early air-insulated RMUs used vacuum or puffer-type load switches from VEI, as well as gas-generating load switches. Later, with the widespread adoption of the SM6 series, it became the mainstream solution for air-insulated RMUs. Similar to other air-insulated RMUs, the key difference lies in replacing the load switch with an SF6-encapsulated type—where the three-position switch for load and grounding is
Echo
11/03/2025
Climate-Neutral 24kV Switchgear for Sustainable Grids | Nu1
Climate-Neutral 24kV Switchgear for Sustainable Grids | Nu1
Expected service life of 30–40 years, front access, compact design equivalent to SF6-GIS, no SF6 gas handling – climate-friendly, 100% dry air insulation. The Nu1 switchgear is metal-enclosed, gas-insulated, featuring a withdrawable circuit breaker design, and has been type-tested according to relevant standards, approved by the internationally recognized STL laboratory.Compliance Standards Switchgear: IEC 62271-1 High-voltage switchgear and controlgear – Part 1: Common specifications for altern
Edwiin
11/03/2025
Related Products
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.