Generator circuit breakers(GCB) role in gas turbine power plants

Edwiin
Edwiin
Field: Power switch
China

When starting a gas - turbine generator, its rotor must first be accelerated by external means to approximately 60% of the rated speed. Only then does the start - up process become self - sustaining, meaning the turbine can generate enough power to continue the process independently. To achieve this initial acceleration, energy can be supplied by various means, with a static frequency converter (SFC) being a common choice.

Generator circuit breakers (GCBs) play a crucial role in this process. They are designed to incorporate the switching functions necessary for SFC - based starting within their enclosures. The output of the SFC, which features a voltage of variable amplitude and frequency, is routed to the generator terminals through a dedicated starting switch. This starting switch is engineered to handle the specific voltage, current, and current duration characteristics that occur during the SFC start - up phase of the gas turbine. Its rated voltage is typically selected based on the rated voltage of the SFC, which is generally much lower than the generator's rated voltage.

The typical layout of a gas turbine power plant is illustrated in the figure below.

  • MT: Main transformer

  • UT: Unit transformer

  • SS: Starting switch

  • SFC: Static frequency converter

  • AUX: Unit auxiliaries

Give a tip and encourage the author!
Recommended
What are the causes of dielectric withstand failure in vacuum circuit breakers?
What are the causes of dielectric withstand failure in vacuum circuit breakers?
Causes of Dielectric Withstand Failure in Vacuum Circuit Breakers: Surface contamination: The product must be thoroughly cleaned before dielectric withstand testing to remove any dirt or contaminants.Dielectric withstand tests for circuit breakers include both power-frequency withstand voltage and lightning impulse withstand voltage. These tests must be performed separately for phase-to-phase and pole-to-pole (across the vacuum interrupter) configurations.Circuit breakers are recommended to be t
Felix Spark
11/04/2025
What are the causes of failures in low-voltage switchgear circuit breakers themselves?
What are the causes of failures in low-voltage switchgear circuit breakers themselves?
Based on years of field statistics on switchgear accidents, combined with analysis focusing on the circuit breaker itself, the main causes have been identified as: failure of operation mechanism; insulation faults; poor breaking and closing performance; and poor conductivity.1.Failure of Operation MechanismFailure of operation mechanism manifests as delayed operation or unintended operation. Since the most basic and important function of a high-voltage circuit breaker is to operate correctly and
Felix Spark
11/04/2025
THD Measurement Error Standards for Power Systems
THD Measurement Error Standards for Power Systems
Error Tolerance of Total Harmonic Distortion (THD): A Comprehensive Analysis Based on Application Scenarios, Equipment Accuracy, and Industry StandardsThe acceptable error range for Total Harmonic Distortion (THD) must be evaluated based on specific application contexts, measurement equipment accuracy, and applicable industry standards. Below is a detailed analysis of key performance indicators in power systems, industrial equipment, and general measurement applications.1. Harmonic Error Standar
Edwiin
11/03/2025
Compact Air-Insulated RMUs for Retrofit & New Substations
Compact Air-Insulated RMUs for Retrofit & New Substations
Air-insulated ring main units (RMUs) are defined in contrast to compact gas-insulated RMUs. Early air-insulated RMUs used vacuum or puffer-type load switches from VEI, as well as gas-generating load switches. Later, with the widespread adoption of the SM6 series, it became the mainstream solution for air-insulated RMUs. Similar to other air-insulated RMUs, the key difference lies in replacing the load switch with an SF6-encapsulated type—where the three-position switch for load and grounding is
Echo