• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


What are the principles of forced re-energization of transmission lines?

Edwiin
Field: Power switch
China

Principles of Forced Re-energization of Transmission Lines

Regulations for Forced Re-energization of Transmission Lines

  • Correctly select the forced re-energization end of the line. If necessary, change the connection configuration before forced re-energization, taking into account the reduction of short-circuit capacity and its impact on grid stability.

  • There must be a transformer with its neutral point directly grounded on the busbar at the forced re-energization end.

  • Pay attention to the impact of forced re-energization on the transient stability of adjacent lines. If necessary, first reduce the load on all lines and units within the dynamic stability range before performing forced re-energization.

  • When a line trips or fails to reclose, accompanied by obvious system oscillation, immediate forced re-energization should not be performed. The oscillation must be checked and eliminated before considering whether to perform forced re-energization.

  • The circuit breaker for forced re-energization and its auxiliary equipment must be in good condition, and protection must be complete and functional.

  • During forced re-energization, busbar differential protection should be selectively put into operation and have backup protection for the connection configuration, ensuring that a failure of the circuit breaker to trip will not result in a complete outage of both busbars. When only one busbar is in operation, forced re-energization of lines should be avoided as much as possible.

Principles of forced re-energization of transmission lines.jpg

The Following Cases Prohibit Forced Re-energization After a Line Trip

  • Standby lines in an unloaded charging state;

  • Lines under trial operation;

  • After a line trip, if the load has already been transferred to other lines via automatic backup power switching, and power supply is unaffected;

  • Cable lines;

  • Lines where live-line work is being performed;

  • Line-transformer group circuit breakers that trip and fail to reclose;

  • When operating personnel have already observed obvious fault phenomena;

  • Lines where the circuit breaker has defects or insufficient interrupting capacity;

  • Lines known to have serious defects (e.g., submerged by water, severely tilted towers, severely broken conductor strands, etc.).

In the Following Cases, Forced Re-energization Must Be Performed Only After Contacting and Obtaining Permission from Dispatch

  • Busbar fault, where no obvious fault point is found after inspection;

  • Ring network line fault trip;

  • One circuit of a double-circuit line trips due to fault;

  • Lines that may cause out-of-phase closing;

  • Transformer backup protection trip.

Give a tip and encourage the author!
Recommended
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.