How primary feeder, distribution transformer, fuses and service operate in radial networks

James
04/11/2025

Preventing an interruption of service

As is known, distribution transformers reduce the distribution or primary feeder voltage to the utilization voltage. They are linked to the primary feeder, sub - feeders, and laterals via primary fuses or fused cutouts. When a transformer fault or a low - impedance secondary - circuit fault takes place, the primary fuse disconnects the associated distribution transformer from the primary feeder. Reclosers are not addressed in this article.

 

The blowing of the primary fuse prevents an interruption of service to other loads supplied over the feeder, but interrupts service to all consumers supplied through its transformer.

Fused cutouts (as shown in Figure 1, which are normally closed) provide a convenient means for disconnecting small distribution transformers for inspection and maintenance.

Due to the difference in the shape of the current - time curve of the primary fuse and the safe current - time curve of the distribution transformer, satisfactory overload protection for the distribution transformer cannot be achieved with a primary fuse. The shapes of these two curves are such that if a small - sized enough fuse is used to provide complete overload protection for the transformer, a great deal of the valuable overload capacity of the transformer will be lost, because the fuse will blow and prevent the transformer from making use of its overload capacity. Moreover, such a small - sized fuse often blows unnecessarily due to surge currents.

Distribution transformers connected to overhead open - wire feeders are often subject to severe lightning disturbances. To minimize insulation breakdown and transformer failures caused by lightning, lightning arresters are generally installed for these transformers.

The secondary leads of a distribution transformer are typically solidly connected to radial secondary circuits. As depicted in Figure 1, consumer services are tapped from these circuits. This connection arrangement implies that the transformer lacks protection against overloads and high - impedance faults in its secondary circuits. In fact, relatively few distribution transformers are damaged by overloads.

This situation mainly stems from the application of distribution transformers, where their overload capacity is seldom fully utilized.

Regarding protection, fuses in the secondary leads of distribution transformers are scarcely more effective than primary fuses in preventing transformer burnouts, and for similar reasons. The appropriate approach to effectively safeguard a distribution transformer against overloads and high - impedance faults is to install a circuit breaker in the transformer's secondary leads. Crucially, the tripping curve of this circuit breaker must be precisely coordinated with the transformer's safe current - time curve.

Faults in a consumer's service connection, which runs from the secondary circuit to the service switch, are extremely rare. Therefore, installing a secondary fuse at the point where the service connection taps into the secondary circuit is not economically viable, except in special circumstances like large - scale services from underground secondary circuits.

As previously mentioned, the allowable voltage drop, measured from the point where the first distribution transformer connects to the primary feeder to the service switch of the last consumer on the feeder, should be economically allocated among the primary feeder, the distribution transformer, the secondary circuit, and the consumer's service connection.

Although these figures are typical for overhead systems that supply residential loads, significant differences can be expected in underground systems. Underground systems often utilize cable circuits and large - scale distribution transformers or are designed to supply industrial and commercial loads.

Once the total allowable voltage drop for the distribution transformer and the secondary circuit is determined, it is relatively easy to figure out the most cost - effective combination of their sizes for any uniform load density and construction type, given specific market prices.

If the transformer is oversized, the cost of the secondary circuit and the overall cost will be exorbitant. Conversely, if the transformer is undersized, the cost of the transformer itself and the overall cost will be too high.

Similar to other components within the distribution system, load fluctuations and growth must be factored into the design and sizing of distribution transformers and secondary circuits. These elements are not merely installed to accommodate the existing loads at the time of installation; they also need to account for future load demands.

Nevertheless, it is not cost - effective to overly anticipate growth.

When a distribution transformer is perilously overloaded, this action also alleviates the load on the overloaded transformer's secondary circuit and enhances the overall voltage regulation. In areas with relatively uniform loads, additional transformers may need to be installed on either side of the overloaded one in a short period. This is necessary to maintain acceptable voltage levels and prevent any part of the secondary circuit from being overloaded.

However, an alternative approach to achieve the same outcome is to install a new transformer and relocate the overloaded transformer so that it supplies power to the mid - section of its shortened secondary circuit.

If the transformer is oversized, the cost of the secondary circuit and the overall cost will be exorbitant. Conversely, if the transformer is undersized, the cost of the transformer itself and the overall cost will be too high.

James

Professionalism builds strength. As an expert in the installation and operation of electrical equipment, I am proficient in the installation process and strictly adhere to standards. I skillfully master the operation essentials and can swiftly eliminate faults. With a heart that constantly explores new knowledge, I illuminate the path to the efficient operation of electrical equipment.

Selection and Application of Small Reactors at the Neutral Point of 500kV Substations
Selection and Application of Small Reactors at the Neutral Point of 500kV Substations
1 Relevant Theories of Small Neutral Point Reactors in 500kV Substations1.1 Definitions and RolesA reactor is a key power system component that controls the phase relationship between AC current and voltage, divided into inductive and capacitive types. Inductive reactors limit short-circuit currents and improve stability; capacitive ones enhance transmission efficiency and voltage quality. A small neutral point reactor is a specialized type connected between a three-phase system's neutral point
Echo
07/25/2025
What are the comprehensive considerations for product selection and installation?
What are the comprehensive considerations for product selection and installation?
In real-world engineering projects, selecting and installing 35kV combined instrument transformers isn't just a matter of "buying and installing" — it requires a comprehensive evaluation of many factors, such as environmental conditions, equipment performance, and maintenance convenience. Only by taking all these aspects into account can we ensure that the equipment runs safely and stably for a long time under specific conditions.1. Oil-Immersed vs. Dry-Type Transformers — Which One
James
07/22/2025
What aspects should be considered when selecting and installing 35kV combined transformers?
What aspects should be considered when selecting and installing 35kV combined transformers?
The installation quality of combined instrument transformers directly affects whether they can operate safely and stably. Therefore, during the installation process, several key aspects must not be overlooked — such as foundation construction, grounding, sealing checks, testing and commissioning, as well as secondary wiring. Below, I’ll explain these points in a more conversational way.1. Foundation Construction Must Be Solid, Especially in Plateau AreasAlthough a combined instrument
James
07/22/2025
A Quick Verification Method for Low-Voltage Current Transformers
A Quick Verification Method for Low-Voltage Current Transformers
1. Selection of Low - Voltage Current Transformer ConfigurationThere are many factors leading to wrong selection of low - voltage current transformers in civil construction projects. For example, common factors include design problems: the calculated coefficient designed for the load of electrical equipment is relatively large, or the transformation ratio of the current transformer is selected incorrectly. Such a series of reasons will affect the use of electrical equipment. Therefore, in the co
James
07/16/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!