• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


How to Test Insulation Resistance of Distribution Transformers

Oliver Watts
Field: Inspection and testing
China

In practical work, insulation resistance of distribution transformers is generally measured twice:

  • the insulation resistance between the high-voltage (HV) winding and the low-voltage (LV) winding plus the transformer tank, and

  • the insulation resistance between the LV winding and the HV winding plus the transformer tank.

If both measurements yield acceptable values, it indicates that the insulation among the HV winding, LV winding, and transformer tank is qualified. If either measurement fails, pairwise insulation resistance tests must be conducted among all three components (HV–LV, HV–tank, LV–tank) to identify which specific insulation path is defective.

1. Preparation of Tools and Instruments

For insulation resistance testing of a 10 kV distribution transformer, the following tools and instruments are required:

  • 2500 V insulation resistance tester (megohmmeter)

  • 1000 V insulation resistance tester

  • Discharge rod

  • Voltage detector (voltage tester)

  • Grounding cables

  • Shorting leads

  • Insulating gloves

  • Adjustable wrench

  • Screwdrivers

  • Lint-free cloth (e.g., gauze)

Before use, inspect all tools and instruments for damage and verify they are within their valid safety test period. Additionally, perform open-circuit and short-circuit tests on the insulation resistance testers to confirm proper operation.

2. Transitioning the Transformer from Service to Maintenance Status

To take a rural distribution transformer out of service for maintenance:

  • Maintenance personnel must complete a work permit, which undergoes step-by-step approval.

  • Upon dispatch authorization, on-site operators disconnect the LV load, open the HV drop-out fuses, and establish a visible disconnection point.

  • Maintenance staff then perform discharge, voltage verification, install grounding lines, and set up barriers and warning signs.

3. Insulation Resistance Measurement

For a transformer already in maintenance status:

  • Remove all HV and LV leads from the bushing terminals.

  • Clean the HV and LV bushings thoroughly with a lint-free cloth to prevent surface contamination from affecting results.

  • Visually inspect bushings for discharge marks or cracks.

  • After cleaning, short together the three HV bushing terminals and the four LV bushing terminals using shorting leads.

Measurement 1: HV winding to LV winding + tank

  • Use a 2500 V insulation resistance tester.

  • Short and ground the transformer tank and LV bushing terminals.

  • Connect the L (line) terminal of the tester to the HV shorting lead.

  • Connect the E (earth) terminal to the LV shorting lead.

  • If bushings are heavily contaminated, connect the G (guard) terminal via a wire wrapped around the HV bushing near the L connection (without touching L), ensuring G remains well insulated from E.

Measurement 2: LV winding to HV winding + tank

  • Use a 1000 V insulation resistance tester.

  • Short and ground the transformer tank and HV bushing terminals.

  • Connect the L terminal to the LV shorting lead.

  • Connect the E terminal to the HV shorting lead.

  • If using the G terminal, wrap its lead around the LV bushing under the same conditions as above.

4. Measurement Precautions

(1) Maintain adequate spacing between L, G, and E leads during wiring. Insufficient separation may cause arcing between leads, increasing leakage current between L and E and compromising measurement accuracy.

(2) The insulation resistance tester delivers its rated voltage only at a cranking speed of 120 rpm. Maintain this speed throughout the test, and continue cranking for at least 1 minute before recording the reading.

(3) The HV winding, LV winding, and tank form a large capacitive system. After taking the reading:
– First disconnect the tester leads from the transformer, then stop cranking. Failure to do so may allow the charged transformer to back-feed into the tester, potentially damaging it.
– Always discharge the transformer thoroughly using a discharge rod before removing any test leads.

(4) After completing the test, record the ambient temperature during measurement and correct the insulation resistance value to 20°C for standardized comparison. Compare the corrected result against applicable code requirements and historical data—no significant deviation should be observed.

Give a tip and encourage the author!
Recommended
Design Principles for Pole-Mounted Distribution Transformers
Design Principles for Pole-Mounted Distribution Transformers(1) Location and Layout PrinciplesPole-mounted transformer platforms should be located near the load center or close to critical loads, following the principle of “small capacity, multiple locations” to facilitate equipment replacement and maintenance. For residential power supply, three-phase transformers may be installed nearby based on current demand and future growth projections.(2) Capacity Selection for Three-Phase Pole-Mounted Tr
12/25/2025
Analysis of Common Faults and Causes in Routine Inspection of Distribution Transformers
Common Faults and Causes in Routine Inspection of Distribution TransformersAs the terminal component of power transmission and distribution systems, distribution transformers play a critical role in supplying reliable electricity to end users. However, many users have limited knowledge of power equipment, and routine maintenance is often carried out without professional support. If any of the following conditions are observed during transformer operation, immediate action should be taken: Excess
12/24/2025
Analysis of Lightning Protection Measures for Distribution Transformers
Analysis of Lightning Protection Measures for Distribution TransformersTo prevent lightning surge intrusion and ensure the safe operation of distribution transformers, this paper presents applicable lightning protection measures that can effectively enhance their lightning withstand capability.1. Lightning Protection Measures for Distribution Transformers1.1 Install surge arresters on the high-voltage (HV) side of the distribution transformer.According to SDJ7–79 Technical Code for Overvol
12/24/2025
Lightning Protection for Distribution Transformers: Arrester Installation Position Analysis
Lightning Protection for Distribution Transformers: Arrester Installation Position AnalysisIn China's economic development, the power system holds an extremely important position. Transformers, as devices utilizing electromagnetic induction to convert AC voltage and current, represent a crucial component of the power system. Lightning damage to distribution transformers is quite common, particularly significant in humid tropical areas with frequent lightning activity. A research team has propose
12/24/2025
Related Products
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.