• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


What Conflicts Exist Between FA and UFLS in Power Systems and How to Solve Them?

RW Energy
RW Energy
Field: Distribution Automation
China

Feeder Automation (FA) and Under-Frequency Load Shedding (UFLS) are two critical protection and control mechanisms in power systems. While both aim to ensure safe and stable system operation, they carry potential conflicts in logic and timing that require careful coordination.

Feeder Automation (FA): Primarily addresses local feeder faults (e.g., short circuits, ground faults) in distribution networks. Its objective is to quickly locate and isolate faulted sections and restore power to non-faulted areas via network reconfiguration using switches. FA emphasizes rapid local power restoration.

Under-Frequency Load Shedding (UFLS): Responds to severe frequency drops in the interconnected grid (e.g., due to generator tripping, sudden load increase, or tie-line disconnection causing power deficit). It systematically sheds pre-designated non-critical loads to prevent frequency collapse, restore power balance, and stabilize system frequency. UFLS prioritizes overall system frequency security.

Under-Voltage Load Shedding (UVLS): Monitors system voltage in real time. When voltage drops below a preset threshold, the UVLS scheme determines whether to act based on predefined logic. If conditions are met, it sequentially sheds loads to reduce reactive power demand or enhance reactive support, thereby restoring voltage to normal levels.

Conflict Case Examples

  • Case 1: In 2019, in North America, FA-induced power restoration triggered a secondary frequency collapse.

  • Case 2: In 2020, in East China, FA operation following a short-circuit fault caused erroneous UFLS activation.

  • Case 3: In 2021, wind farm disconnection triggered overlapping actions between UFLS and FA.

  • Case 4: In 2022, during a typhoon in South China, FA network reconfiguration led to excessive load shedding.

Event Description

In 2022, 110kV Line A and a power plant’s grid-connected Line B were operating on Bus Section I of a 110kV substation. A fault on Line A caused Switch A to trip. However, since the plant’s Line B switch remained closed, power continued to be supplied to the substation. As a result, the voltage on Bus Section I did not fall below the undervoltage threshold, preventing the 110kV automatic transfer switch (ATS) from initiating. Similarly, the plant supplied power via Transformer No. 1 to the 10kV Buses I and IV, whose voltages also remained above threshold, so the 10kV ATS did not activate.

As the plant continued to supply load, system frequency gradually declined. 5.3 seconds after Switch A tripped, frequency dropped to 48.2 Hz. The plant’s under-voltage and under-frequency separation device, set at 47 Hz and 0.5 s, did not operate. However, the substation’s UFLS relay, set at 48.25 Hz and 0.3 s, detected the frequency of 48.12 Hz and operated correctly, shedding several 10kV feeders (Lines C, D, E, F, G). All secondary equipment operated as expected.

On-site Review

The 110kV substation’s Switch A tripped correctly due to protection action, and UFLS operated, disconnecting Lines C, D, E, F, and G. The substation switches issued trip signals, triggering FA activation. The fault was identified between the substation switch and the first line switch. FA initiated on all five lines, locating the fault between the substation outlet and the first switch. However, no fault was found during on-site inspection, confirming a false FA operation.

Solution

  • Enhance synchronization of load shedding information. For lines with UFLS/UVLS protection, support blocking of automatic load transfer functions.

  • Implement robust load transfer blocking: in fully automatic centralized FA schemes, upon receiving a load shedding signal, immediately block the FA execution function for the affected lines.

Give a tip and encourage the author!
Recommended
SST Technology: Full-Scenario Analysis in Power Generation, Transmission, Distribution, and Consumption
SST Technology: Full-Scenario Analysis in Power Generation, Transmission, Distribution, and Consumption
I. Research BackgroundPower System Transformation NeedsChanges in energy structure are placing higher demands on power systems. Traditional power systems are transitioning toward new-generation power systems, with the core differences between them outlined as follows: Dimension Traditional Power System New-Type Power System Technical Foundation Form Mechanical Electromagnetic System Dominated by Synchronous Machines and Power Electronic Equipment Generation-Side Form M
Echo
10/28/2025
Rectifier vs Power Transformer: Key Differences
Rectifier vs Power Transformer: Key Differences
Differences Between Rectifier Transformers and Power TransformersRectifier transformers and power transformers both belong to the transformer family, but they differ fundamentally in application and functional characteristics. The transformers commonly seen on utility poles are typically power transformers, while those supplying electrolytic cells or electroplating equipment in factories are usually rectifier transformers. Understanding their differences requires examining three aspects: working
Echo
10/27/2025
SST Transformer Core Loss Calculation and Winding Optimization Guide
SST Transformer Core Loss Calculation and Winding Optimization Guide
SST High-Frequency Isolated Transformer Core Design and Calculation Material Characteristics Impact:Core material exhibits varying loss behavior under different temperatures, frequencies, and flux densities. These characteristics form the foundation of overall core loss and require precise understanding of nonlinear properties. Stray Magnetic Field Interference:High-frequency stray magnetic fields around windings can induce additional core losses. If not properly managed, these parasitic losses
Dyson
10/27/2025
Upgrade Traditional Transformers: Amorphous or Solid-State?
Upgrade Traditional Transformers: Amorphous or Solid-State?
I. Core Innovation: A Dual Revolution in Materials and StructureTwo key innovations:Material Innovation: Amorphous AlloyWhat it is: A metallic material formed by ultra-rapid solidification, featuring a disordered, non-crystalline atomic structure.Key Advantage: Extremely low core loss (no-load loss), which is 60%–80% lower than that of traditional silicon steel transformers.Why it matters: No-load loss occurs continuously, 24/7, throughout a transformer’s lifecycle. For transformers with low loa
Echo
10/27/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.