I. Introduction
The Guanting–Lanzhou East 750kV transmission and substation demonstration project in China was officially put into operation on September 26, 2005. This project includes two substations—Lanzhou East and Guanting (each equipped with four 750kV transformers, three of which form a three-phase transformer bank in operation, with one on standby)—and one transmission line. The 750kV transformers used in the project were independently developed and manufactured in China. During the on-site commissioning tests, excessive partial discharge (PD) was detected in the Phase A main transformer at Lanzhou East Substation. A total of 12 PD tests were conducted before and after commissioning. This paper analyzes the reference standards, procedures, data, and issues related to the PD tests of this transformer, and offers practical engineering recommendations to support future on-site testing of 750kV and 1000kV transformers.
II. Basic Transformer Parameters
The main transformer at Lanzhou East Substation was manufactured by Xi’an XD Transformer Co., Ltd. Key parameters are as follows:
Model: ODFPS-500000/750
Rated Voltage: HV 750kV, MV (with ±2.5% tap changer) kV, LV 63kV
Rated Capacity: 500/500/150 MVA
Maximum Operating Voltage: 800/363/72.5 kV
Cooling Method: Forced oil circulation with air cooling (OFAF)
Oil Weight: 84 tons; Total Weight: 298 tons
HV Winding Insulation Level: Full-wave impulse 1950kV, chopped-wave impulse 2100kV, short-time induced withstand voltage 1550kV, power frequency withstand voltage 860kV
III. Test Procedure and Standards
(A) Test Procedure
According to GB1094.3-2003, the partial discharge test procedure for transformers consists of five time periods—A, B, C, D, and E—with specified applied voltages for each. The pre-stress voltage during the C period is defined as 1.7 per unit (pu), where 1 pu = Um/√3 (Um being the maximum system voltage). This value is slightly lower than Um specified in GB1094.3-1985. For the Lanzhou East transformer, Um = 800kV, so the pre-stress voltage should be 785kV.
(B) Withstand Voltage Requirements
The short-time induced withstand voltage for the Lanzhou East transformer is 860kV. According to the State Grid Corporation of China's "Commissioning Test Standards for 750kV UHV Electrical Equipment," the on-site test voltage should be 85% of the factory test value, i.e., 731kV, which is less than the required pre-stress voltage of 1.7 pu (785kV).
To resolve the conflict between pre-stress voltage and ommissioning withstand voltage, relevant standards state that if the pre-stress voltage exceeds 85% of the factory withstand voltage, the actual pre-stress voltage should be agreed upon by the user and manufacturer. The "Technical Specification for 750kV Main Transformers" explicitly specifies that the on-site PD test pre-stress voltage equals 85% of the factory withstand voltage. As a result, the pre-stress voltage for the on-site PD test of the Lanzhou East transformer was set at 731kV. The PD measurement and withstand test were combined, with the withstand test phase serving as the pre-stress stage of the PD test.
(C) Acceptance Criteria for Partial Discharge
Under a test voltage of 1.5 pu, the transformer's partial discharge level must be less than 500 pC.
IV. Test Process
From August 9, 2005, to April 26, 2006, a total of 12 PD tests were conducted on the Phase A main transformer at Lanzhou East Substation. Key test information is summarized below:
Test No. |
Date |
Withstand Test? |
PD Level |
Remarks |
1 |
2005-08-09 |
Yes |
HV: 180pC, MV: 600–700pC |
Pre-commissioning; MV slightly exceeds limit |
2 |
2005-08-10 |
No |
700pC (>100kV, at 1.5pu) |
Pre-commissioning |
3 |
2005-08-10 |
No |
700pC (>100kV, at 1.5pu) |
Pre-commissioning |
4 |
2005-08-12 |
Yes |
688pC (>100kV, at 1.5pu) |
Pre-commissioning |
5 |
2005-08-12 |
No |
600pC (>100kV, at 1.5pu) |
Pre-commissioning |
6 |
2005-08-15 |
No |
700pC (>100kV, at 1.5pu) |
Pre-commissioning |
7 |
2005-08-16 |
No |
700pC (>100kV, at 1.5pu) |
Pre-commissioning |
8 |
2005-08-17 |
No |
700pC (>100kV, at 1.5pu) |
Pre-commissioning |
9 |
2005-08-21 |
No |
500pC (power frequency, 1.05pu, 48h) |
Pre-commissioning; included 48h no-load test |
10 |
2005-08-24 |
No |
667pC (>100kV, at 1.5pu) |
Pre-commissioning |
11 |
2005-09-23 |
Yes |
910pC (>100kV, at 1.5pu) |
Pre-commissioning; PD level slightly increased |
12 |
2006-04-26 |
Yes |
280pC (>100kV, at 1.5pu) |
Post-commissioning; MV PD level reduced to acceptable range |
Overall, the PD level of the MV winding of Phase A main transformer before commissioning ranged between 600 and 910 pC, exceeding the 500 pC acceptance criterion. However, after retesting on April 26, 2006, following commissioning, the PD level dropped to 280 pC, meeting the requirement.
V. Test Analysis
(A) Partial Discharge Inception Voltage (PDIV) and Extinction Voltage (PDEV)
Definition Issues: GB7354-2003 and DL417-1991 provide imprecise definitions of PDIV and PDEV. For instance, the "specified value" in the definition is not clearly defined—though 500pC is commonly assumed, this leads to significant inconsistencies in practical application. Additionally, background noise during on-site tests often reaches tens to hundreds of picocoulombs, making it difficult to identify a clear onset of discharge.
Case Observations: In the 12 PD tests conducted on the Lanzhou East Phase A transformer, the PD level increased gradually with voltage, without a distinct jump (maximum step change ~200pC), making it impossible to determine a clear PDIV. In some tests, measurable PD was already present at low voltages, making it difficult to assess whether PDIV had decreased. Moreover, the latest national standard GB1094.3-2003 does not mention PDIV or PDEV, leading to inconsistent interpretation and determination among practitioners.
(B) Discharge Localization
Limitations of Common Methods: The widely used ultrasonic PD localization method detects the time difference of ultrasonic waves generated by discharges arriving at sensors on the tank wall. However, this method faces challenges such as immature technology, requirement for sufficiently large discharge energy (within sensor sensitivity range), and inaccurate localization due to multiple reflections and refractions of ultrasonic waves from inner windings.
Case Results: During pre-commissioning tests, PD localization equipment provided only a rough estimate of the discharge location. The control room monitoring system failed to detect PD variations with voltage, limiting the usefulness of the results. Later-installed online monitoring systems also failed to detect relevant changes during the April 26, 2006 test. Therefore, ultrasonic localization results should be treated with caution when PD levels are low.
(C) Severity of Discharge
Although the standard specifies a 500pC limit at 1.5 pu, in practice, there is no significant difference between 500pC and 700pC—they belong to the same order of magnitude. Moreover, when PD is below 1000pC, there is typically no visible discharge trace inside the transformer, and on-site oil drainage inspections rarely reveal abnormalities. Returning a 750kV transformer (large and heavy) to the factory for repair carries high risks.
VI. Recommendations
(A) Increase Insulation Level
The induced withstand voltage of the Lanzhou East transformer is relatively low. Considering the short history and limited experience in domestic 750kV transformer manufacturing, along with the necessity of on-site PD tests, it is recommended that future 750kV main transformers have an induced withstand voltage of no less than 900kV.
(B) Relax On-Site Commissioning PD Test Criteria
Overseas, PD tests are strictly performed only at the factory, not repeated on-site. In China, however, on-site PD testing is a mandatory commissioning item. It is recommended to relax the acceptance criterion for on-site PD tests of 750kV transformers to less than 1000pC, for the following reasons:
Transformers with PD levels between 500–1000pC often show reduced PD upon retesting after a period of storage or operation (e.g., Lanzhou East Phase A transformer).
When PD is below 1000pC, no visible discharge traces are typically found, on-site inspections rarely detect issues, and factory return poses high risks.
On-site PD tests for 750kV and 1000kV transformers are effectively "quasi-withstand tests":
Small voltage margin: For the Lanzhou East transformer, the PD test voltage at 1.5 pu (693kV, ±3% measurement uncertainty: 672–714kV) is very close to the commissioning withstand voltage of 731kV, leaving only a 2.4% margin. Even if future 750kV transformers have an induced withstand voltage raised to 900kV, the commissioning test at 765kV still leaves limited margin. Similarly, for 1000kV transformers, the PD test voltage (1.4 pu = 889kV) is very close to the 935kV withstand level.
Long duration: While the standard withstand duration is only about 56 seconds (at 108Hz test frequency), the full PD test applies 1.5 pu for up to 65 minutes. Repeated testing may cause cumulative insulation damage, affecting transformer lifespan.
There are few cases where repeated on-site tests reduce excessive PD to acceptable levels; instead, PD levels may increase (e.g., Lanzhou East Phase A transformer: 700pC on August 10, 2005, increased to 910pC by September 23).
(C) Redefine PD Inception and Extinction Voltages
Existing standards lack clear definitions for PDIV and PDEV, which can mislead test interpretation (as seen in the Lanzhou East case). It is recommended to redefine these terms with explicit numerical criteria and include guidance for cases where PDIV and PDEV are not clearly observable.
(D) Strengthen Research on Practical On-Site Techniques
Collect Real Transformer PD Patterns: Most typical PD patterns in literature are from laboratory simulations, which differ from real transformer behavior. Illustrative diagrams are insufficient for guiding field work. It is essential to collect and analyze real-world PD patterns and compile them into reference manuals for qualitative analysis and localization.
Advance Anti-Interference Research: External interference is a major challenge in on-site PD testing. Current measurement systems cannot distinguish between genuine discharges and interference, relying heavily on operator experience. More research is needed on interference sources and suppression methods.
(E) Require Certification for Test Personnel
PD measurement is the most technically demanding and unpredictable of routine on-site high-voltage tests. However, misjudgments are common. Personnel should undergo systematic training in fundamental principles, equipment wiring, component matching, interference elimination, and PD localization, and must obtain certification before being allowed to conduct tests.
(F) Regular Calibration of Test Instruments
GB7354-2003 clearly states that PD measuring instruments must be calibrated at least twice a year or after major repairs. In practice, this is often not strictly followed, with some instruments used for years without calibration—errors as high as tens of times have been recorded. Strict enforcement of calibration per national standards is recommended to ensure measurement accuracy.
(G) Use Online Monitoring When Necessary
Online monitoring technology has significantly improved. For 750kV transformers with PD levels exceeding limits but not critically high, enhanced online monitoring is a reasonable approach. In addition to PD, parameters such as temperature, core and clamp grounding current, and oil chromatography should be monitored to comprehensively assess transformer health.
VII. Conclusion and Outlook
Conclusion: Existing standards provide inadequate definitions for PD inception and extinction voltages,limiting their usefulness in guiding on-site tests. The insulation level of the Lanzhou East 750kV transformer is relatively low, making its PD test essentially a "quasi-withstand" test. The 12 on-site PD tests on the Phase A transformer likely caused some cumulative insulation stress. Future 750kV transformers should have an insulation level of at least 900kV.
Outlook: Research and planning for China’s 1000kV AC ultra-high-voltage transmission have been completed, and demonstration projects are under construction. Given the even smaller insulation margin of 1000kV transformers, research into on-site commissioning tests should be initiated early to provide technical support for practical applications.