What is tha Impulse Test of Transformer?

Encyclopedia
08/09/2024

The purpose of the pulse test

Detection of partial discharge

Partial discharge refers to the discharge phenomenon that occurs at the air gap or impurity in the insulation material under the action of high voltage electric field, which may gradually destroy the insulation system.

Evaluate the degree of insulation aging

By analyzing the characteristics of partial discharge, you can evaluate the degree of aging of the insulation material.

Identify potential insulation failures

Problems such as moisture, filth, bubbles, or mechanical damage.

Method of pulse test

Pulse Current Method (PCM) 

Principle: By applying a short high-voltage pulse, the partial discharge inside the transformer is excited, and the pulse current generated by the partial discharge is captured.

Equipment: Using a pulse current tester, this instrument is capable of generating high voltage pulses and capturing current pulses generated by partial discharge.

Procedure

  • Disconnect the power supply to the transformer.

  • Connect the pulse current tester to the winding of the transformer.

  • A high voltage pulse is applied and the current pulse generated by the partial discharge is captured.

  • The pulse current waveform is analyzed to determine the characteristics of partial discharge.

Pulse Voltage Method (PVM) 

Principle: By applying high voltage pulse, the partial discharge is excited and the voltage change generated by the partial discharge is captured.

Equipment: Using a pulse voltage tester, this instrument is capable of generating high voltage pulses and capturing voltage changes generated by partial discharge.

Procedure

  • Disconnect the power supply to the transformer.

  • Connect the pulse voltage tester to the winding of the transformer.

  • A high-voltage pulse is applied and the voltage change generated by the partial discharge is captured.

  • The voltage waveform is analyzed to determine the characteristics of partial discharge.

Test considerations

Safety first: Since high pressure is involved, safety procedures must be strictly followed during testing.

Environmental conditions: The test should be carried out in a dry, dust-free environment to reduce external interference.

Equipment calibration: Test equipment should be calibrated regularly to ensure the accuracy of test results.

Data analysis

Partial discharge level: The severity of partial discharge can be assessed by analyzing the amplitude and frequency distribution of pulsed current or voltage.

Pattern recognition: Through pattern recognition technology, different types of partial discharge can be distinguished, so as to locate the cause of the fault.

Trend analysis: Through trend analysis of data from multiple tests, it is possible to monitor changes in the health of the transformer insulation system over time.

Encyclopedia

The Electricity Encyclopedia is dedicated to accelerating the dissemination and application of electricity knowledge and adding impetus to the development and innovation of the electricity industry.

Cost Differences and Performance Comparison of 35kV New Energy Transformers Based on Dry-Type, Mineral Oil, and Vegetable Oil
Cost Differences and Performance Comparison of 35kV New Energy Transformers Based on Dry-Type, Mineral Oil, and Vegetable Oil
For users, when purchasing a 35kV new energy transformer, choosing between dry-type, mineral oil-filled, or vegetable oil-filled types involves multiple considerations. These include user habits, maintenance-free performance, safety and fire resistance, volume and weight, among others. However, cost differences are undoubtedly one of the most crucial factors.To illustrate the issue intuitively, this paper selects a three-level energy efficiency dual-winding new energy transformer with a rated ca
Ron
07/26/2025
What is the connection group of a transformer?
What is the connection group of a transformer?
Transformer Connection GroupThe connection group of a transformer refers to the phase difference between the primary and secondary voltages or currents. It is determined by the winding directions of the primary and secondary coils, the labeling of their start and end terminals, and the connection mode. Expressed in a clock-like format, there are 12 groups in total, numbered from 0 to 11.The DC method is commonly used to measure the transformer's connection group, mainly to verify whether the con
Vziman
07/26/2025
What is the sequence for powering down the transformer?
What is the sequence for powering down the transformer?
The sequence for shutting down a main transformer is as follows: when de-energizing, the load side should be shut down first, followed by the power supply side. For energizing operations, the reverse order applies: the power supply side is energized first, then the load side. This is because: Energizing from the power supply side to the load side makes it easier to identify the fault range and take prompt judgment and handling measures in case of a fault, preventing the fault from spreading or e
Rockwell
07/26/2025
What are the methods for switching operations of station transformers?
What are the methods for switching operations of station transformers?
Let's take an auxiliary power system with two station transformers as an example. When one station transformer needs to be out of service, there are two operation methods: non-interruptive power supply and instantaneous power interruption. Generally, the method of instantaneous power interruption on the low-voltage side is preferred.The operation method for instantaneous power interruption on the low-voltage side is as follows:Open the 380V power incoming circuit breaker of the corresponding sec
Vziman
07/26/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!