• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Analysis and Handling of Insulation Breakdown Faults in 35kV Outdoor Vacuum Circuit Breakers

Felix Spark
Field: Failure and maintenance
China

Equipment Description

The ZW7 - 40.5 type outdoor high - voltage vacuum circuit breaker is an outdoor - installed, three - phase, AC 50 Hz high - voltage electrical equipment that uses vacuum as the arc - extinguishing medium. It is mainly used for switching the rated current and fault current in the 40.5 kV high - voltage power transmission and distribution system [1], and is especially suitable for places where frequent operations are required.

The overall structure of this product is of the porcelain bushing pillar type, as shown in Figure 1. The upper porcelain bushing is the porcelain bushing of the vacuum interrupter, in which the vacuum interrupter is installed, and the lower porcelain bushing is the supporting porcelain bushing. Both the porcelain bushing of the vacuum interrupter and the supporting porcelain bushing are filled with vacuum insulating grease with excellent insulating properties. The three - phase porcelain bushings are installed on a single framework together.
 
The three - phase current transformers are installed within this framework and are respectively connected to the main circuit of the circuit breaker inside the three - phase supporting porcelain bushings. The framework is equipped with sealing plates on all four sides and at the bottom to adapt to the outdoor environment.
 
The moving end of the vacuum interrupter is connected to the output shaft of the operating mechanism through a crank arm and an insulating pull rod. The opening and closing operations of the circuit breaker, as well as the control and protection wiring, are led out by the components and terminals inside the mechanism box. The three - phase linkage operation is achieved through the operating structure and the transmission structure.
Figure 1 Structure diagram of vacuum circuit breaker

Analysis of the Fault Causes

On March 18, 2010, during the routine condition - based maintenance of the equipment in a certain substation, the testing personnel found that an insulation breakdown occurred in phase A of the 3515 vacuum circuit breaker (model: ZW7 - 40.5/T1250 - 25) during the AC withstand voltage test.

The testing personnel carried out relevant analysis and tests regarding the insulation breakdown in phase A of the 3515 circuit breaker. The specific data are shown in Table 1 as follows:
According to the routine test regulations of the State Grid Corporation, the insulation resistance of vacuum circuit breakers at 35 kV and above should not be lower than 3000 MΩ, and the AC withstand voltage test voltage should be 80% of the factory - tested value, that is, 76 kV/min. Before the testing personnel conducted the withstand voltage test on the 3515 vacuum circuit breaker, the insulation resistance of the main circuit in all three phases met the requirements of the regulations.
 
Subsequently, the testing personnel conducted AC withstand voltage tests on the main circuits of the three phases respectively. It was found that when the voltage of phase A's main circuit rose to 35 kV, the current increased instantaneously and a breakdown occurred.
After this phenomenon occurred, the testing personnel carried out the following tests based on the structure of this type of circuit breaker:
  • The vacuum circuit breaker was opened, and an insulation resistance test was carried out on the upper porcelain bushing of the circuit breaker. The test data met the requirements of the regulations, confirming that the defective part was in the lower porcelain bushing.
  • An insulation resistance test was carried out on the lower porcelain bushing. The test data did not meet the requirements of the regulations, further confirming that the defective part was in the lower porcelain bushing.
  • The lower porcelain bushing consisted of the lower porcelain bushing body, the insulating tie - rod, and the supporting porcelain vase. Therefore, the testing personnel disconnected the crank arm between the insulating tie - rod and the supporting porcelain vase, and carried out insulation resistance tests on the insulating tie - rod and the supporting porcelain vase respectively. The insulation resistances of both the supporting porcelain vase and the insulating tie - rod met the requirements of the regulations, determining that the defective part was in the lower porcelain bushing body.
  • The lower porcelain bushing body included vacuum insulating grease and current transformers. The decrease in insulation resistance might be caused by the dampness of the vacuum insulating grease and the breakdown of the current transformers.

Fault Handling

At the end of October 2010, the manufacturer disassembled and inspected the phase A circuit breaker. The test steps and results were as follows:
  • The upper porcelain bushing and the support of the vacuum circuit breaker were removed, and an insulation resistance test was directly carried out inside the supporting porcelain vase. The test results verified that the above - mentioned analysis was accurate.
  • The vacuum insulating grease and the current transformers of the vacuum circuit breaker were separated, and insulation resistance tests were carried out on them respectively. The insulation resistance of the vacuum insulating grease was about 50 MΩ, while the insulation resistance of the current transformers met the requirements of the regulations. It was determined that the insulation breakdown was caused by the vacuum insulating grease.
  • After replacing the vacuum insulating grease, insulation resistance and AC withstand voltage tests were carried out on phase A of the vacuum circuit breaker. The test data all met the requirements of the regulations.

 Preventive Measures

The external insulation of the ZW7 - 40.5 type vacuum circuit breaker uses vacuum insulating grease, which is a liquid insulating medium. During the operation and installation of the equipment, the moisture content of the liquid medium will increase. The moisture is in a suspended state in the insulating grease of the electrical equipment. Under the action of the electric field force, the water will gradually arrange itself into a "bridge" along the electric lines of force.
 
This "bridge" runs through the two poles and is likely to significantly reduce the breakdown voltage. This also explains why the insulation resistance was quite low under a 5 kV voltage during the telemetry of insulation resistance, but this hidden danger was not exposed under the operating voltage.
Through the above - mentioned analysis, in order to avoid the fault of insulation breakdown caused by the dampness of the vacuum insulating grease of the vacuum circuit breaker, the following preventive measures are proposed:
  • Install the equipment in strict accordance with the assembly process to avoid the mixing of impurities and prevent the medium from coming into contact with the atmosphere. 
  • Strengthen the inspection efforts and conduct partial discharge tests using an ultraviolet tester.
  • Conduct tests in strict accordance with the electrical test regulations, including seal - tightness testing, vacuum - degree testing, insulation testing, etc.
Give a tip and encourage the author!
Recommended
Ultimate Guide to AC Contactor Abnormal Noise: From Electromagnetic Noise to Mechanical Vibration, Accurate Diagnosis and Handling
In electrical control systems, AC contactors are among the commonly used electrical components, and they are also a common source of various electrical faults. After long-term use—especially in harsh environments with high levels of dust—AC contactors may sometimes emit squeaking or rattling noises after being pulled in and held. The causes of this phenomenon are analyzed as follows.Squeaking Noise After Pull-In and HoldingA fully functional AC contactor makes no noise when energized and pulled
Felix Spark
09/11/2025
Comprehensive Guide to High-Frequency Fault Handling of AC Contactors: 90% of Problems Solved with One Method
1. Fault Phenomena, Cause Analysis and Handling MethodsContactor does not operate or operates abnormally after coil energization Open circuit in coil control circuit; Check if there is wire breakage or loosening at the terminal blocks. If there is a wire breakage, replace the corresponding wire; if there is loosening, fasten the corresponding terminal block. Coil damage; Measure the coil resistance with a multimeter. If the resistance is ∞, replace the coil. Thermal relay not reset after operati
Felix Spark
09/11/2025
Application and Maintenance of AC Contactors | Comprehensive Analysis of Common Fault Handling, Master It in One Article
1 Analysis of Key Components of AC ContactorsAn AC contactor is an automated electromagnetic switch used for long-term, high-frequency switching of AC main circuits and control circuits. It features advantages such as automatic operation, under-voltage and no-voltage protection, high-capacity operation, strong stability, and low maintenance requirements. In the electrical control circuits of machine tools, AC contactors are mainly used to control electric motors and other loads.The key component
Felix Spark
09/11/2025
Dielectric Withstand Capability of AC Vacuum Contactors and Countermeasures
During operation, AC vacuum contactors are often subjected to various overvoltages such as lightning overvoltage and switching overvoltage. Therefore, AC vacuum contactors must have a certain voltage withstand capacity.An AC vacuum contactor is composed of a vacuum interrupter (its structure is shown in Figure 1), a housing, an electromagnetic system, a secondary circuit, and other components. Among these, the vacuum interrupter is the "heart" of the AC vacuum contactor, and its performance dire
Felix Spark
09/09/2025
Related Products
Seed Inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.