Load Flow or Power Flow Analysis

Electrical4u
Field: Basic Electrical
0
China

What Is Power Flow Analysis

It is the computational procedure (numerical algorithms) required to determine the steady state operating characteristics of a power system network from the given line data and bus data.

load flow or power flow analysisThings you must know about load flow:

  • Load flow study is the steady state analysis of power system network.

  • Load flow study determines the operating state of the system for a given loading.

  • Load flow solves a set of simultaneous non linear algebraic power equations for the two unknown variables (|V| and ∠δ ) at each node in a system.

  • To solve non linear algebraic equations it is important to have fast, efficient and accurate numerical algorithms.

  • The output of the load flow analysis is the voltage and phase angle, real and reactive power (both sides in each line), line losses and slack bus power.

Load Flow Steps

The study of load flow involves the following three steps:

  • Modeling of power system components and network.

  • Development of load flow equations.

  • Solving the load flow equations using numerical techniques.

Modeling of Power System Components

Generator
modeling of power system components

Load
modeling of power system components
Transmission Line
A
Transmission line is represented as a nominal π model.

Where, R + jX is the line impedance and Y/2 is called the half line charging admittance.

Off Nominal Tap Changing Transformer
For a nominal transformer the relation
But for an off nominal transformer
Thus for an off nominal transformer we define the transformation ratio (a) as follows

Now we would like to represent an off nominal transformer in a line by an equivalent model.
line containing an off nominal transformerFig 2: Line Containing an Off Nominal Transformer
We want to convert the above into an equivalent π model between bus p and q.
equivalent π model of lineFig 3: Equivalent π Model of Line

Our aim is to find these values of admittances Y1, Y2 and Y3 so that fig2 can be represented by fig 3
From Fig 2 we have,

Now consider Fig 3, from fig3 we have,
From eqn I and III on comparing the coefficients of Ep and Eq we get,
Similarly from equation II and IV we have
Some useful observations
From above analysis we see that Y2, Y3 values can either be positive or negative depending on the value of transformation ratio.
Good question!
Y = – ve implies absorption of reactive power i.e it is behaving as an
inductor.
Y = + ve implies generation of reactive power i.e it is behaving as a
capacitor.
Modeling of a Network
modeling of a networkConsider the two bus system as shown in figure above.
We have already seen that
Power generated at bus i is
Power demand at bus i is

Therefore we define the net power injected at bus i as follows

Give a tip and encourage the author!

Recommended

Main Transformer Accidents and Light Gas Operation Issues
1. Accident Record (March 19, 2019)At 16:13 on March 19, 2019, the monitoring background reported a light gas action of No. 3 main transformer. In accordance with the Code for Operation of Power Transformers (DL/T572-2010), operation and maintenance (O&M) personnel inspected the on-site condition of No. 3 main transformer.On-site confirmation: The WBH non-electrical protection panel of No. 3 main transformer reported a Phase B light gas action of the transformer body, and the reset was ineff
02/05/2026
Faults and Handling of Single-phase Grounding in 10kV Distribution Lines
Characteristics and Detection Devices for Single-Phase Ground Faults1. Characteristics of Single-Phase Ground FaultsCentral Alarm Signals:The warning bell rings, and the indicator lamp labeled “Ground Fault on [X] kV Bus Section [Y]” illuminates. In systems with a Petersen coil (arc suppression coil) grounding the neutral point, the “Petersen Coil Operated” indicator also lights up.Insulation Monitoring Voltmeter Indications:The voltage of the faulted phase decreases (in
01/30/2026
Neutral point grounding operation mode for 110kV~220kV power grid transformers
The arrangement of neutral point grounding operation modes for 110kV~220kV power grid transformers shall meet the insulation withstand requirements of transformer neutral points, and shall also strive to keep the zero-sequence impedance of substations basically unchanged, while ensuring that the zero-sequence comprehensive impedance at any short-circuit point in the system does not exceed three times the positive-sequence comprehensive impedance.For 220kV and 110kV transformers in new constructi
01/29/2026
Why Do Substations Use Stones, Gravel, Pebbles, and Crushed Rock?
Why Do Substations Use Stones, Gravel, Pebbles, and Crushed Rock?In substations, equipment such as power and distribution transformers, transmission lines, voltage transformers, current transformers, and disconnect switches all require grounding. Beyond grounding, we will now explore in depth why gravel and crushed stone are commonly used in substations. Though they appear ordinary, these stones play a critical safety and functional role.In substation grounding design—especially when multiple gr
01/29/2026
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.