Electronic Current Transformer (ECT) Solution:​​ ​Economically Driven Retrofit

07/24/2025

I. Pain Points: Challenges in Conventional Substation Retrofit
Traditional electromagnetic current transformers (CTs) present numerous issues in aging substations:

  • High Retrofit Cost:​ Replacing conventional CTs requires large-scale power outages, civil construction, and updates to protection panels, cabling, and grounding systems. Combined costs exceed 50%.
  • Poor Compatibility:​ New devices have interface mismatches with legacy secondary systems (e.g., relays, meters), necessitating additional conversion devices.
  • Space Constraints:​ Aging substations have limited space. Conventional CTs are bulky and heavy, making hoisting difficult and potentially requiring foundation expansion.
  • Lengthy Commissioning:​ Retrofits involve multi-system integration testing. Tight outage windows delay grid restoration.

II. Solution: ECT (Electronic Current Transformer) Economical Retrofit
Achieve an upgrade path of "minimizing retrofit cost, maximizing compatibility with existing systems" through ECT technology:

​**▶ Core Economic Advantage: Significant Reduction in Comprehensive Retrofit Cost**​

Cost Item

Conventional CT Retrofit

ECT Retrofit Solution

Cost Savings

Equipment Installation

Crane/Civil Works/Foundation Reinforcement

Direct Stud Mounting

​**↓ 40% construction cost**​

Cabling

Multi-strand Copper Cables + Extensive Wiring

Fiber Optic / Digital Signal Lines

​**↓ 60% cable cost**​

Secondary Equipment Interface Retrofit

Protection Panels & Meter Replacement Required

Compatible with Traditional Analog Output

​**↓ 80% secondary retrofit cost**​

Outage Duration

≥7 Days (Full Substation Shutdown)

≤3 Days (Partial Outage)

​**↓ 50% outage loss**​

​**▶ Compatibility Design: Seamless Integration with Existing Infrastructure**​

  1. Hybrid Interface Output:
    ECTs feature built-in ​Analog Output (4-20mA/0-5V) + Digital Output (IEC 61850-9-2), compatible with three scenarios:
    • Legacy Protection Devices:​ Connect directly to existing current input terminals.
    • Digital Protection Systems:​ Send GOOSE messages via Merging Units (MUs).
    • Metering Systems:​ Simultaneously output analog signals for meter sampling.
  2. Plug-and-Play Installation:
    • No Crane Required:​ ECT weight <15kg (vs. ~150kg for conventional CTs), enabling manual installation.
    • Compact Size:​ Diameter ≤200mm, fits original CT mounting brackets.
    • Flexible Rogowski Coil:​ Can be wrapped around existing primary conductors, eliminating busbar disassembly.
  3. Adaptive Power Supply Scheme:
    • Laser Power Supply:​ Energy delivered via fiber optics embedded in insulators, eliminating separate power supplies.
    • Busbar Power Harvesting:​ Inductive power harvesting uses primary current for self-supply, suitable for passive environments.

III. Value Realization: Rapid Return on Retrofit Investment

Retrofit Phase

Core Value of ECT Solution

Economic Impact

Pre-construction & Construction

Shortens Schedule by 70%

Reduces Outage Loss ≥ ¥2 million

Commissioning

Plug-and-play, no calibration for legacy protection

Commissioning Costs ​**↓60%​**​

Operation & Maintenance

No magnetic saturation, wideband measurement (0.1Hz~5kHz)

Maintenance Frequency Reduced by ​90%

Long-term Expansion

Pre-installed digital interfaces support future smart substation upgrades

Avoids secondary retrofit investment

IV. Representative Case Study: 110kV Gudu Substation Retrofit

  • Original Configuration:​ Electromagnetic CTs (Commissioned 1985)
  • Retrofit Solution:
    Installed 12 ECTs (Class ±0.5S) to replace conventional CTs. Output signals:
    → 4-20mA fed into existing relay protection devices.
    → IEC 61850-9-2LE fed into newly installed smart control cabinets.
  • Economic Results:
    • Total Investment Reduced by 42%​ (Primarily saved on cabling, civil works, commissioning).
    • Outage Time Reduced​ from originally planned 7 days to ​2.5 days.
    • Compatibility Verified:​ Conventional differential protection operating time maintained at ​15ms, with ​no failure to trip / maloperation.

V. Why Choose the ECT Economical Retrofit?

  1. Controlled Cost:​ Retrofit budget reduced by ​30%-50%, ​ROI < 3 years.
  2. Risk Mitigation:​ Maintains existing protection logic, avoiding system reconfiguration risks.
  3. Smooth Evolution:​ Compatible with today's analog systems, supporting tomorrow's digital grid.
  4. Emergency Replacement:​ Faulty CT replacement completed in as little as ​48 hours.
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!