• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


An GIS Equipment Explosion Accident Caused by PT Secondary Wiring Errors

Felix Spark
Field: Failure and maintenance
China

1. Accident Overview

A newly - built 110kV substation’s GIS exploded during commissioning due to a PT secondary circuit short - circuit. Though the cause was simple, consequences were severe, warranting reflection.

2. Accident Process

On the power - transmission day:

  • The upper - level power supply charged the 110kV GIS (a combined appliance).

  • 20s after closing the incoming switch and first live - impacting the 110kV bus, white smoke emerged between the PT compartment and control cabinet.

  • Within ten seconds, the bus PT’s GIS compartment exploded. The upper power tripped; the PT compartment’s disc insulator burst, filling the GIS room with insulator fragments and SF₆ combustion by - products.

3. Cause Analysis
3.1 On - site Investigation

The 110kV PT (Shanghai MWB, electromagnetic type) had:

  • 1 basic secondary winding: 100/√3 V (150VA, 0.2 class).

  • 1 auxiliary secondary winding: 100V (150VA, 3P class), unused per design (routed to the control cabinet terminal block, no external connection).

Key findings:

  • Phase C: Severe PT secondary winding insulation burns; basic winding conductor charred. Auxiliary winding conductor insulation totally burned; insulation cylinder between auxiliary winding & iron core charred. Insulation resistance between basic & auxiliary windings = 0.

  • Phase B: Basic secondary winding outer insulation had burning marks; internal paint film intact. Auxiliary winding surface insulation showed overheating charring.

  • Phase A: Slight basic secondary winding surface insulation burn; other conductors/insulation intact.

Preliminary conclusion: PT secondary circuit short - circuit, likely in B/C phase auxiliary windings.

Further control cabinet inspection: B/C phase auxiliary windings were shorted inside. Design - intended connections (C - ncf to terminal 11, B - nbf to terminal 15) were misrouted (C - ncf to 12, shorting to 14 - cf; B - nbf to 16, shorting to 18 - bf).

3.2 Accident Development

  • Short - circuit start: After primary system closure, B/C phase auxiliary windings (cf, ncf; bf, nbf) shorted → B/C voltage drop.

  • B phase short - circuit end: After 20s, B phase short - circuit disconnected (primary lead burned by arc). Short time caused only B auxiliary winding overheating.

  • C phase consequence: 43s short - circuit (per accident recording) overheated C phase secondary conductor → insulation melt/char. White smoke came from this.

  • Insulation failure: PT auxiliary winding insulation melt degraded SF₆ gas in the PT chamber → lower insulation level.

  • Discharges: Reduced insulation + close phase - to - ground distances → A/B/C phases discharged to GIS shell.

  • Explosion: Arc energy raised gas chamber pressure → PT disc insulator burst.

3.3 Human Error

During commissioning:

  • Technicians rechecked PT polarity/insulation.

  • For convenience, they removed the PT secondary circuit from the control cabinet terminal block.

  • Mistakenly shorted B/C phase auxiliary winding ends; failed to verify → B/C auxiliary windings shorted.

4. Preventive Measures
4.1 PT Secondary Circuit Safety

Short - circuits in PT secondary circuits damage components or burn PTs. Installed in a closed GIS chamber, PT faults cause explosions (risking injury, delaying repairs). Thus, GIS PT installation/wiring demands strict attention.

4.2 Secondary Circuit Protocols

“Electrical Safety Work Regulations” and “Relay Protection On - site Work Security Regulations” mandate secondary work safety tickets for disassembly/wiring. Using these (and integrating risk control) could have prevented wrong wiring amid workload/time pressures.

4.3 Pre - energization Testing

Strengthen pre - energization PT tests (standardized, documented). Enforce strict test execution to avoid errors from careless work.

4.4 Organizational & Protection Measures

Protect commissioned equipment (lock cabinets, use seals). Modify only post - approval; have supervised restoration.

4.5 Unused Circuit Removal

Remove unused secondary circuits (reduce error risks). Here, the unused auxiliary winding (routed to the control cabinet) caused the accident via miswiring.

4.6 PT Body Air Switch

Install secondary air switches in PT body wiring boxes (current setup in control cabinets can’t protect GIS - to - PT circuits). This isolates faults below the PT secondary outlet.By reconstructing the accident, analyzing causes, and proposing 6 preventive measures, a roadmap for GIS secondary circuit safety is established.

Give a tip and encourage the author!
Recommended
Ultimate Guide to AC Contactor Abnormal Noise: From Electromagnetic Noise to Mechanical Vibration, Accurate Diagnosis and Handling
In electrical control systems, AC contactors are among the commonly used electrical components, and they are also a common source of various electrical faults. After long-term use—especially in harsh environments with high levels of dust—AC contactors may sometimes emit squeaking or rattling noises after being pulled in and held. The causes of this phenomenon are analyzed as follows.Squeaking Noise After Pull-In and HoldingA fully functional AC contactor makes no noise when energized and pulled
Felix Spark
09/11/2025
Comprehensive Guide to High-Frequency Fault Handling of AC Contactors: 90% of Problems Solved with One Method
1. Fault Phenomena, Cause Analysis and Handling MethodsContactor does not operate or operates abnormally after coil energization Open circuit in coil control circuit; Check if there is wire breakage or loosening at the terminal blocks. If there is a wire breakage, replace the corresponding wire; if there is loosening, fasten the corresponding terminal block. Coil damage; Measure the coil resistance with a multimeter. If the resistance is ∞, replace the coil. Thermal relay not reset after operati
Felix Spark
09/11/2025
Application and Maintenance of AC Contactors | Comprehensive Analysis of Common Fault Handling, Master It in One Article
1 Analysis of Key Components of AC ContactorsAn AC contactor is an automated electromagnetic switch used for long-term, high-frequency switching of AC main circuits and control circuits. It features advantages such as automatic operation, under-voltage and no-voltage protection, high-capacity operation, strong stability, and low maintenance requirements. In the electrical control circuits of machine tools, AC contactors are mainly used to control electric motors and other loads.The key component
Felix Spark
09/11/2025
Dielectric Withstand Capability of AC Vacuum Contactors and Countermeasures
During operation, AC vacuum contactors are often subjected to various overvoltages such as lightning overvoltage and switching overvoltage. Therefore, AC vacuum contactors must have a certain voltage withstand capacity.An AC vacuum contactor is composed of a vacuum interrupter (its structure is shown in Figure 1), a housing, an electromagnetic system, a secondary circuit, and other components. Among these, the vacuum interrupter is the "heart" of the AC vacuum contactor, and its performance dire
Felix Spark
09/09/2025
Seed Inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.