What is the result of connecting three phase transformers in parallel?

Encyclopedia
12/09/2024

Results of Parallel Operation of Three-Phase Transformers

Parallel operation of two or more three-phase transformers is a common configuration in power systems, aimed at increasing system capacity, reliability, and flexibility. However, transformers must meet certain conditions to ensure safe, stable, and efficient parallel operation. Below are the results of parallel operation of three-phase transformers and related considerations.

1. Conditions for Parallel Operation

To ensure that three-phase transformers can operate safely in parallel, the following conditions must be met:

  • Equal Rated Voltages: The rated voltages on both the high-voltage and low-voltage sides of the transformers must be identical. If the voltages do not match, it can lead to unbalanced currents or overloading.

  • Same Turns Ratio: The turns ratio (the ratio of the high-voltage side to the low-voltage side) of the transformers must be the same. If the ratios differ, it will result in inconsistent secondary voltages, causing circulating current, increased losses, and reduced efficiency.

  • Identical Connection Groups: The connection types (such as Y/Δ, Δ/Y, etc.) of the three-phase transformers must be the same. Different connection groups can cause phase differences, leading to circulating currents or uneven power distribution.

  • Similar Short-Circuit Impedance: The short-circuit impedance of the parallel-operating transformers should be as close as possible. If there is a significant difference in short-circuit impedance, the load distribution will be uneven, potentially causing one transformer to become overloaded while another remains underloaded.

  • Same Frequency: The transformers must operate at the same frequency. This is typically ensured by connecting them to the same power grid.

2. Results of Parallel Operation

a. Increased Capacity

Total Capacity: When multiple transformers are operated in parallel, the total system capacity is the sum of the individual transformer capacities. For example, two 500 kVA transformers operating in parallel provide a total capacity of 1000 kVA. This allows the system to handle larger load demands.

b. Load Distribution

Ideal Load Distribution: In an ideal scenario, where all parallel-operating transformers meet the above conditions (especially having similar short-circuit impedance), the load will be evenly distributed among the transformers. Each transformer will carry an equal share of the load current, ensuring stable system operation.

Non-Ideal Load Distribution: If the short-circuit impedances of the transformers differ, the load distribution will be uneven. Transformers with lower short-circuit impedance will carry more of the load, while those with higher impedance will carry less. This uneven distribution can lead to some transformers becoming overloaded, affecting system reliability and lifespan.

c. Circulating Currents

Generation of Circulating Currents: If the parallel-operating transformers do not meet the above conditions (such as different turns ratios, connection groups, or short-circuit impedance), circulating currents may occur between the transformers. Circulating current refers to the flow of current between transformers in the absence of external loads. Circulating currents increase system losses and can cause transformers to overheat, reducing their lifespan.

Impact of Circulating Currents: The presence of circulating currents reduces the effective output capacity of the transformers because part of the current is used for internal circulation rather than supplying the load. Additionally, circulating currents can cause the transformers to heat up, increasing the risk of failure.

d. Improved Reliability

Redundancy: Parallel operation of transformers provides redundancy. If one transformer fails or requires maintenance, the others can continue to supply power, ensuring continuous system operation. This enhances the overall reliability and availability of the power system.

e. Cost Efficiency

Flexible Expansion: By operating in parallel, the system's capacity can be increased incrementally without replacing existing transformers. This is a cost-effective solution for gradually expanding power systems.

Backup Capacity: Parallel-operating transformers can provide backup capacity. Under normal conditions, all transformers share the load, but if one transformer fails, the others can temporarily handle the additional load, avoiding system interruption.

3. Considerations for Parallel Operation

a. Protective Devices

Differential Protection: To prevent circulating currents or other abnormal conditions during parallel operation, differential protection devices are typically installed. Differential protection detects differences in current between the transformers and can quickly isolate a faulty transformer to protect the system.

b. Monitoring and Control

  • Load Monitoring: Parallel-operating transformers should be equipped with load monitoring equipment to continuously track the load on each transformer, ensuring even load distribution. If uneven loading is detected, adjustments should be made promptly.

  • Temperature Monitoring: Since parallel operation can lead to some transformers becoming overloaded, it is important to monitor the temperature of the transformers to prevent overheating and damage.

c. Maintenance and Inspection

  • Regular Checks: Parallel-operating transformers should undergo regular inspections and maintenance to ensure optimal performance. Particular attention should be paid to checking the short-circuit impedance, connection groups, and other parameters to ensure they remain consistent for parallel operation.

  • Fault Isolation: If one transformer fails, it should be immediately isolated from the system to avoid affecting the operation of the other transformers.

4. Summary

Parallel operation of three-phase transformers can significantly increase system capacity, reliability, and flexibility, but strict conditions must be met, such as equal rated voltages, turns ratios, connection groups, and short-circuit impedance. If these conditions are satisfied, the load will be evenly distributed among the transformers, and the system will operate stably. However, if these conditions are not met, issues such as circulating currents and uneven load distribution can arise, impacting system efficiency and safety.

Parallel operation also provides redundancy, allowing the system to continue operating even if one transformer fails, and offers a cost-effective solution for gradual system expansion.

Encyclopedia

The Electricity Encyclopedia is dedicated to accelerating the dissemination and application of electricity knowledge and adding impetus to the development and innovation of the electricity industry.

Cost Differences and Performance Comparison of 35kV New Energy Transformers Based on Dry-Type, Mineral Oil, and Vegetable Oil
Cost Differences and Performance Comparison of 35kV New Energy Transformers Based on Dry-Type, Mineral Oil, and Vegetable Oil
For users, when purchasing a 35kV new energy transformer, choosing between dry-type, mineral oil-filled, or vegetable oil-filled types involves multiple considerations. These include user habits, maintenance-free performance, safety and fire resistance, volume and weight, among others. However, cost differences are undoubtedly one of the most crucial factors.To illustrate the issue intuitively, this paper selects a three-level energy efficiency dual-winding new energy transformer with a rated ca
Ron
07/26/2025
What is the connection group of a transformer?
What is the connection group of a transformer?
Transformer Connection GroupThe connection group of a transformer refers to the phase difference between the primary and secondary voltages or currents. It is determined by the winding directions of the primary and secondary coils, the labeling of their start and end terminals, and the connection mode. Expressed in a clock-like format, there are 12 groups in total, numbered from 0 to 11.The DC method is commonly used to measure the transformer's connection group, mainly to verify whether the con
Vziman
07/26/2025
What is the sequence for powering down the transformer?
What is the sequence for powering down the transformer?
The sequence for shutting down a main transformer is as follows: when de-energizing, the load side should be shut down first, followed by the power supply side. For energizing operations, the reverse order applies: the power supply side is energized first, then the load side. This is because: Energizing from the power supply side to the load side makes it easier to identify the fault range and take prompt judgment and handling measures in case of a fault, preventing the fault from spreading or e
Rockwell
07/26/2025
What are the methods for switching operations of station transformers?
What are the methods for switching operations of station transformers?
Let's take an auxiliary power system with two station transformers as an example. When one station transformer needs to be out of service, there are two operation methods: non-interruptive power supply and instantaneous power interruption. Generally, the method of instantaneous power interruption on the low-voltage side is preferred.The operation method for instantaneous power interruption on the low-voltage side is as follows:Open the 380V power incoming circuit breaker of the corresponding sec
Vziman
07/26/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!